Projects to be Let in the Next 6 Months - By Parish
PLEASE NOTE:
Projects TENTATIVELY scheduled to be let within the next 6 months. The Letting Dates are contingent upon availability of funds and completion of all pre-construction activities.
| Parish | Letting Date |
Project | Route | Project Name | Type Improvement | Estimated Cost Range |
Length (miles) |
Project Manager |
|---|---|---|---|---|---|---|---|---|
| Acadia | 2013-06-12 | H.009622 | LA 1111 | La 1111: Rt Turn Lane @ La 13 | Construct Right Turn Lane | $500,000 to $1,000,000 | 0.15 | Deville, Jacques |
| Acadia | 2013-06-30 | H.010073 | Bnsf (Crowley) Several Crossings | R2 Railroad Signalization | $500,000 to $1,000,000 | 0.00 | Shrewsberry,Bill | |
| Ascension | 2013-06-26 | H.009637 | I-10 | I-10: East Baton Rouge P/L - La 22 | Pccp Patching & Slope Repairs | $1,000,000 to $2,500,000 | 14.49 | Thomas, Ben |
| Ascension | 2013-08-14 | H.010182 | LA 42 | La 42 Widening: Clear, Grub & Utility | Clearing and Grubbing With Utility Work | $5,000,000 to $7,500,000 | 3.61 | Kendrick, Brian |
| Ascension | 2013-08-14 | H.010714 | LA 22 | La 22 Isaac Er Embankment Repair | Repair Slope Failure & Apply Abutment Protection From Scour | $500,000 to $1,000,000 | 0.04 | Cavalier, Stephanie |
| Ascension | 2013-10-01 | H.010074 | LA 3089 | Up (Donaldsonville) La 3089 Service Rd. | Road Work Around Crossing to Make Safer | $0 to $100,000 | 0.00 | Shrewsberry,Bill |
| Ascension | 2013-10-23 | H.010642 | LA 30 | La 30: Iberville Pl to 0.3m West Of I-10 | Cold Plane and Overlay | $1,000,000 to $2,500,000 | 6.45 | Riggs, Laura |
| Ascension, East Baton Rouge | 2013-06-27 | H.010831 | LA 37, LA 935, LA 431 | La 37/La 935/La 431: Enhanc. Pvmt Mrks | Restriping With Thermoplastic Edge and Center Line and Instl | $100,000 to $250,000 | 11.04 | Shahla, Walid |
| Ascension, St. James | 2013-10-09 | H.010752 | LA 22, LA 70 | La 70 & La 22: Pavement&drainage Improv | La22 Nbltl Extens, La70 Sbltl Extens & Nbrtl Addn, La70 Rcb | $1,000,000 to $2,500,000 | 0.66 | Deville, Jacques |
| Assumption | 2013-06-12 | H.006006 713-04-0002 |
Highway 400 Bridge Over Cancienne Canal | Bridge Replacement | $500,000 to $1,000,000 | 0.00 | Pentek, Gary | |
| Assumption | 2013-06-12 | H.009423 | LA 69 | La 69: Chevrons and Restriping | Add Chevrons to 2 Curves and Restripe | $250,000 to $500,000 | 2.76 | Vasquez, Marta |
| Assumption | 2013-08-14 | H.007867 804-24-0008 |
LA 1012 | Himalaya Canal Bridge | Bridge Replacement | $500,000 to $1,000,000 | 0.01 | Bucci, Mark |
| Assumption | 2013-09-03 | H.010846 | Roadway Departure Safety Improvements | Purchase and Install Regulatory & Warning Signs | $0 to $100,000 | 0.00 | Holm, Rick | |
| Avoyelles | 2013-05-22 | H.009487 | LA 1 | La 1 Atchafalaya Bridge Clean & Paint | Cleaning & Painting | $10,000,000 to $15,000,000 | 0.75 | Tullier, Danny |
| Avoyelles | 2013-06-26 | H.001263 052-30-0014 |
LA 1 | Mansura - Marksville | Widen to 4 Lanes | $15,000,000 to $20,000,000 | 3.19 | Tsai, Loong Shen |
| Avoyelles, Rapides | 2013-09-11 | H.007876 805-19-0007 |
LA 1177 | Bayou Boeuf Bridge | Bridge Replacement | $1,000,000 to $2,500,000 | 0.15 | Brauner, Kurt |
| Beauregard | 2013-05-22 | H.010427 | LA 109, LA 389 | La109 & La389: W Jct La389-calcasieu P/L | Patch, Widen and Overlay | $2,500,000 to $5,000,000 | 8.40 | Chenevert, Mark |
| Beauregard | 2013-06-26 | H.006037 713-06-0124 |
Parish Line Road Bridge Over Flat Creek | Bridge Replacement | $500,000 to $1,000,000 | 0.00 | Pentek, Gary | |
| Beauregard | 2013-06-30 | H.010615 | Kcs (Singer) RR X-ing Near Singer | Railroad Signalization | $250,000 to $500,000 | 0.00 | Shrewsberry,Bill | |
| Beauregard | 2013-08-01 | H.010088 | Kcs (Deridder) Several RR X-ing Deridder | Railroad Signalization | $500,000 to $1,000,000 | 0.00 | Shrewsberry,Bill | |
| Bienville | 2013-06-12 | H.001706 090-05-0028 |
LA 155 | La 155: La 796 - Jackson Parish Line | Widen and Overlay | $1,000,000 to $2,500,000 | 4.56 | Chenevert, Mark |
| Bienville | 2013-06-26 | H.010255 | I-20 | I-20: Tree Removal In Bienville Parish | Tree Removal Along I-20 In Bienville Parish | $250,000 to $500,000 | 17.39 | Baugh, Sam |
| Bienville | 2013-08-14 | H.000126 001-06-0045 |
US 80 | Kcs Railroad Overpass Near Ada | Bridge Replacement | $10,000,000 to $15,000,000 | 0.80 | Nickel, Tim |
| Bienville | 2013-08-14 | H.002578 294-04-0013 |
LA 516 | Madden Mill Cr & Black Lake Bayou Bridge | Bridge Replacement | $2,500,000 to $5,000,000 | 0.40 | Yang, Li |
| Bienville | 2013-09-11 | H.010097 | LA 783 | La 783: Red River Parish Line to US 371 | Overlay, Striping and Related Work | $1,000,000 to $2,500,000 | 3.47 | Chenevert, Mark |
| Bienville | 2013-10-17 | H.010595 | Louisiana Trail - Castor to Jamestown | Construction Of a Multi-use Trail. | $100,000 to $250,000 | 0.00 | Horton, Valerie | |
| Bienville, Bossier, Caddo, Webster | 2013-10-09 | H.010837 | I-20, I-220 | I-20 & I-220: Pavement Marking Replace I | Repl Pave Markings On I-20 & I-220 In Caddo, Boss, Web, Bien | $1,000,000 to $2,500,000 | 46.81 | Colvin, Jody |
| Bienville, Caddo | 2013-09-11 | H.010684 | I-20 | I-20: Cable Barrier In Bienville & Caddo | Install Median Cable Barrier | $2,500,000 to $5,000,000 | 36.83 | Allen, Jeffrey |
| Bossier | 2013-06-26 | H.010624 | I-220 | I220 Phase2 Sign Upgrade - La 538 to I20 | Phase 2 Of I-220 Signing Upgrades | $5,000,000 to $7,500,000 | 9.32 | Courtier, Kay |
| Bossier | 2013-06-30 | H.010609 | Kcs (Bossier) Bodcau Station Rd. | Railroad Signalization | $250,000 to $500,000 | 0.00 | Shrewsberry,Bill | |
| Bossier | 2013-07-10 | H.000397 044-02-0017 |
LA 3 | Union Pacific RR O/P Near Benton | Bridge Replacement | $10,000,000 to $15,000,000 | 1.01 | Delatte, Brian |
| Bossier | 2013-09-11 | H.003263 451-02-0097 |
I-20 | I-20, Westerfield - Industrial | Bridges Rehab. | $30,000,000 to $50,000,000 | 3.66 | Olivier, Nicholas |
| Bossier | 2013-10-09 | H.001156 044-01-0053 |
LA 3 | La 3 Acceleration Lane | Adding an Acceleration Lane | $250,000 to $500,000 | 0.10 | Sturdivant, Phillip |
| Bossier | 2013-10-09 | H.007085 742-08-0001 |
Shed Road (Benton - Airline) | Reconstruction & Widen | $7,500,000 to $10,000,000 | 0.00 | Riggs, Laura | |
| Bossier | 2013-10-29 | H.009120 | Bossier City Inter Safety Improvements | Purchase and Install Signs and Solar Beacons | $0 to $100,000 | 0.00 | Holm, Rick | |
| Bossier, Webster | 2013-07-10 | H.010675 | I-20 | Dist. 04: I-20 Median Cable Barrier | Install Median Cable Barriers On I-20 In Dist. 04 | $2,500,000 to $5,000,000 | 34.73 | Allen, Jeffrey |
| Caddo | 2013-05-08 | H.009398 | LA 3132 | La 3132: Linwood to I-49 (Weave Lane) | Restriping With Minor Widening | $250,000 to $500,000 | 0.41 | Sturdivant, Phillip |
| Caddo | 2013-06-12 | H.009503 | LA 169 | La 169: Gamm Road to US 71 | Asphalt Overlay, Drainage, Pavement Striping & Related Work | $1,000,000 to $2,500,000 | 2.27 | Chenevert, Mark |
| Caddo | 2013-06-26 | H.010301 | LA 1, US 80 | Resurfacing Roads In Caddo | Cold Plane, Superpave Asphaltic Concrete, Pavement Striping | $1,000,000 to $2,500,000 | 4.60 | Chenevert, Mark |
| Caddo | 2013-06-28 | H.010686 | LA 169 | La 169: Kcs RR Xing (Caddo) | Kcs Signal Work Needed to Tie Into La 169 Active Advance Wrn | $0 to $100,000 | 0.01 | Shrewsberry,Bill |
| Caddo | 2013-07-10 | H.001278 053-09-0053 |
LA 3032, LA 1 | Intersection Impr Youree Dr At Kings Hwy | Intersection Improvement | $5,000,000 to $7,500,000 | 0.93 | Riggs, Laura |
| Caddo | 2013-08-14 | H.000101 001-01-0027 |
US 80 | U. P. Railroad Overpass Near Greenwood | New Bridge | $2,500,000 to $5,000,000 | 0.15 | Yap, Kian |
| Caddo | 2013-08-14 | H.000102 001-01-0028 |
US 80 | Cross Bayou and Relief Bridges | Bridge Replacement | $2,500,000 to $5,000,000 | 0.57 | Musa, Elnur |
| Caddo | 2013-08-14 | H.009089 | LA 526 | La 526: Kingston Rd to Linwood Ave. | Adding Turn Lanes | $1,000,000 to $2,500,000 | 0.49 | Baugh, Sam |
| Caddo | 2013-08-14 | H.009578 | I-49 | I-49: La 526 to I-20 | Pcc Patching & Pavement Markings | $500,000 to $1,000,000 | 6.55 | Thomas, Ben |
| Caddo | 2013-08-28 | H.009507 | LA 168 | La 168: La 1 - US 71 | Asphalt Overlay, Drainage, Pavement Striping & Related Work | $2,500,000 to $5,000,000 | 6.56 | Chenevert, Mark |
| Caddo | 2013-09-11 | H.010302 | LA 1, US 71 | Us 71 & La 1: La 3094 to Pine Hills Road | Cold Plane, Superpave Asphaltic Concrete, Pavement Striping | $1,000,000 to $2,500,000 | 3.63 | Allen, Jeffrey |
| Calcasieu | 2013-05-08 | H.002034 193-06-0038 |
LA 14, I-210 | I-210 Short Term Improvements | Add Rt Turn Lane Sb La 14 | $1,000,000 to $2,500,000 | 0.80 | Nickel, Tim |
| Calcasieu | 2013-06-12 | H.009618 | I-10 | I-10:interchange@la 1256-ruth St,Sulphur | Pcc Patching | $500,000 to $1,000,000 | 1.38 | Thomas, Ben |
| Calcasieu | 2013-06-12 | H.010151 | I-210 | Cove Lane Interchange | Proposed Interchange Or Imp. Between Cove Ln. & Nelson Rd. | $30,000,000 to $50,000,000 | 1.80 | Nickel, Tim |
| Calcasieu | 2013-06-26 | H.007116 742-10-0130 |
Sale Road Bridge | Reconstruction | $2,500,000 to $5,000,000 | 0.00 | Hanks, Anna | |
| Calcasieu | 2013-09-11 | H.006478 737-10-0116 |
Signal @ Kirkman & Alamo Streets | Traffic Signal Installation | $250,000 to $500,000 | 0.00 | Monaghan, Terri | |
| Calcasieu | 2013-10-09 | H.010836 | I-10, I-210 | I-10: Pavement Marking Replacement II | Replace Pavement Markings On I-10 In Calcasieu Parish. | $500,000 to $1,000,000 | 37.87 | Colvin, Jody |
| Calcasieu | 2013-10-23 | H.006058 713-10-0110 |
Miller Avenue Bridge Over Gum Slough | Bridge Replacement | $500,000 to $1,000,000 | 0.00 | Pentek, Gary | |
| Caldwell | 2013-06-12 | H.009601 | LA 846 | La 846: La 4 - Ouachita Line | Asphaltic Surface Treatment | $1,000,000 to $2,500,000 | 17.96 | Chenevert, Mark |
| Caldwell | 2013-07-10 | H.010303 | LA 847 | La 847: US 165 - La 133 | Stabilize Base & Overlay | $1,000,000 to $2,500,000 | 5.41 | Chenevert, Mark |
| Caldwell | 2013-10-09 | H.010304 | LA 849 | La 849: La 126 - US 165 | Patch & Overlay | $2,500,000 to $5,000,000 | 9.39 | Chenevert, Mark |
| Caldwell | 2013-10-11 | H.010581 | Grayson Recreation Park Trail | Construction Of a Ped Nature Trail. | $0 to $100,000 | 0.00 | Horton, Valerie | |
| Cameron | 2013-06-26 | H.009477 | LA 27 | Kelso Bridge Electrical Repairs | Electrical Repair | $100,000 to $250,000 | 0.05 | Goodson, Robert |
| Catahoula | 2013-06-12 | H.001138 041-02-0031 |
LA 124 | Booth Rd. - Enterprise | Patch and Overlay | $1,000,000 to $2,500,000 | 4.24 | Chenevert, Mark |
| Catahoula | 2013-06-12 | H.001909 143-05-0024 |
LA 124, LA 3264 | Catahoula Parish Resurfacing Projects | Base & Overlay | $5,000,000 to $7,500,000 | 19.87 | Chenevert, Mark |
| Catahoula | 2013-06-26 | H.001120 039-03-0015 |
LA 8 | Ouachita River Bridge(Harrisonburg) | Bridge Replacement | $30,000,000 to $50,000,000 | 1.35 | Yap, Kian |
| Catahoula | 2013-08-28 | H.006062 713-13-0103 |
Amyx Road Bridge Over Salem Creek | Bridge Replacement | $250,000 to $500,000 | 0.00 | Pentek, Gary | |
| Catahoula | 2013-10-09 | H.001137 041-02-0030 |
LA 124 | La 124 Realignment @ Ouachita River | Roadway Realignment | $1,000,000 to $2,500,000 | 0.80 | Rabalais, Nick |
| Catahoula, Concordia | 2013-09-11 | H.010305 | LA 129, LA 907, LA 3203, LA 908 | La 3203, La 129, La 907& La 908 Overlays | Patch, Overlay & Asphaltic Surface Treatment | $2,500,000 to $5,000,000 | 14.30 | Chenevert, Mark |
| Claiborne | 2013-09-11 | H.006492 737-14-0102 |
Claiborne Parish Rd Signage Upgrade | Reg & Warning Sign Installation | $250,000 to $500,000 | 0.00 | Monaghan, Terri | |
| Claiborne, Webster | 2013-07-10 | H.009514 | LA 532, LA 518 | La 518 & La 532 Overlays | Asphalt Overlay, Drainage, Pavement Striping & Related Work | $2,500,000 to $5,000,000 | 10.42 | Chenevert, Mark |
| Concordia | 2013-05-22 | H.009890 | LA 565 | La 565: La 129 - La 15 | Patch Failures and Resurface With Microsurfacing | $500,000 to $1,000,000 | 8.48 | Mason, Ken |
| Concordia | 2013-06-26 | H.004010 700-15-0109 |
John Williamson Road Bridge Over Creek | Bridge Replacement | $250,000 to $500,000 | 0.00 | Pentek, Gary | |
| DeSoto | 2013-06-30 | H.009886 | Kcs (Mansfield) | Install F/L's and Gates At Jefferson | $100,000 to $250,000 | 0.00 | Shrewsberry,Bill | |
| DeSoto | 2013-07-10 | H.000729 021-01-0004 |
US 84 | Sabine River Br & Appr (Logansport) | Bridge Replacement | $7,500,000 to $10,000,000 | 0.73 | Tsai, Loong Shen |
| DeSoto | 2013-07-10 | H.001073 035-04-0013 |
LA 175 | La175: Kcs Railway Overpass | Bridge Replacement | $2,500,000 to $5,000,000 | 0.60 | Musa, Elnur |
| DeSoto | 2013-08-30 | H.010692 | Cavalier Dr: Kcs RR Xing (Desoto) | Install F/L's and Gates | $100,000 to $250,000 | 0.00 | Shrewsberry,Bill | |
| DeSoto | 2013-09-11 | H.009137 | US 171 | Us 171: Median Improvements | Median Opening Improvements and Turn Lanes | $1,000,000 to $2,500,000 | 1.40 | Harrouch, Joshua |
| DeSoto, Sabine | 2013-06-26 | H.002589 300-02-0004 |
LA 483 | La 174 - Desoto Parish Line | Ctb & Overlay | $1,000,000 to $2,500,000 | 4.33 | Chenevert, Mark |
| District 02 | 2013-09-27 | H.010744 | Alt Fuel Vehicles & Idle Reduct (No Rpc) | Purchase Of Alt Fuel Vehicles,Conv Of Exist Veh,Idle Reduc | $1,000,000 to $2,500,000 | 0.00 | Carney, James | |
| District 04 | 2013-09-11 | H.010139 | Dist. 04: Guard Rail Upgrade | Guard Rail Upgrade | $1,000,000 to $2,500,000 | 0.00 | Baugh, Sam | |
| District 05 | 2013-06-26 | H.010483 | District 05: Districtwide Guardrail | District 05 Guardrail | $1,000,000 to $2,500,000 | 0.00 | Hicks, Melvin | |
| District 58 | 2013-06-12 | H.010029 | District 58 Guard Rail (Vertical Stripe) | Apply Retroflective Traffic Paint to Guard Rail For Safety | $250,000 to $500,000 | 0.00 | Colvin, Jody | |
| East Baton Rouge | 2013-06-12 | H.006500 737-17-0025 |
Baton Rouge Riverfront Devlopement Trans | Bike/Pedestrian Pathway | $1,000,000 to $2,500,000 | 0.00 | Fletcher, Curtis | |
| East Baton Rouge | 2013-06-12 | H.010704 | LA 42 | La 42 (Burbank Dr.) Restriping | Restriping La 42 From 4 Lane Undivided to 5-lane With Twltl | $0 to $100,000 | 0.82 | Allain, Peter |
| East Baton Rouge | 2013-06-26 | H.007137 742-17-0131 |
Jones Cr. Rd.(Tiger Bend - Coursey) | Widen to 5 Lanes | $15,000,000 to $20,000,000 | 0.00 | Riggs, Laura | |
| East Baton Rouge | 2013-06-26 | H.009950 | I-10 | I-10 Miss R Br Baton Rouge (Pier 5 Rep.) | Rep to Pier 5 Pier Protection System Due to Barge Collision | $500,000 to $1,000,000 | 0.01 | Brauner, Kurt |
| East Baton Rouge | 2013-08-01 | H.010554 | Saint Gabriel Trail At the Levee, Ph 2 | Construction Of a Ped-bike Trail On the Miss. River Levee. | $100,000 to $250,000 | 0.00 | Horton, Valerie | |
| East Baton Rouge | 2013-08-14 | H.010232 | I-10, I-110 | I-10/I-110 Br Repairs Ramps Ii-2 & Ii-3 | Repair Columns On I-10 Eb Ramp and Bridge Rail On I-110 | $250,000 to $500,000 | 0.60 | D'andrea, Artur |
| East Baton Rouge | 2013-09-11 | H.002290 744-17-0042 |
LA 64 | La 64: La 19 to Mchugh Rd | Center Turn Lane | $2,500,000 to $5,000,000 | 0.94 | Musa, Elnur |
| East Baton Rouge | 2013-10-09 | H.010648 | Acadian Thruway/N. Acadian Thruway Ovly | Pavement Rehabilitation | $2,500,000 to $5,000,000 | 0.00 | Riggs, Laura | |
| East Baton Rouge | 2013-10-09 | H.010649 | Ebr Parishwide Signal Modifications | Signal Modifications | $1,000,000 to $2,500,000 | 0.00 | Riggs, Laura | |
| East Baton Rouge | 2013-10-11 | H.010585 | Downtown Baton Rouge Greenway Ph. 2 | Construction Of a Ped-bike Trail. | $100,000 to $250,000 | 0.00 | Horton, Valerie | |
| East Baton Rouge, East Feliciana, St. James, West Baton Rouge | 2013-06-12 | H.010717 | US 61, LA 70, LA 68, LA 415 | D61: Chip&removal Of H. Isaac Veg.Debris | Chip & Removal Of Hurricane Issac Vegetative Debris | $0 to $100,000 | 0.04 | Coco, Greg |
| East Baton Rouge, Iberville | 2013-10-09 | H.010833 | I-10, I-110 | I-10 & I-110: Pavement Marking Replace I | Replace Pavement Markings On I-10 and I-110 In Ebr Parish | $500,000 to $1,000,000 | 20.64 | Colvin, Jody |
| East Baton Rouge, West Baton Rouge | 2013-07-10 | H.009943 | Us190: Miss R Br Clean, Paint, Rep-ph II | Repair and Painting Of Railroad Approaches On Bridge | $15,000,000 to $20,000,000 | 0.00 | Guidry, Chris | |
| East Carroll | 2013-06-12 | H.006501 737-18-0001 |
Town Of Lake Providence Sign Proj | Reg & Warning Sign Installation | $0 to $100,000 | 0.00 | Monaghan, Terri | |
| Franklin | 2013-08-14 | H.010487 | LA 863 | La 863: La 4 - La 578 | Widen & Overlay | $500,000 to $1,000,000 | 2.37 | Chenevert, Mark |
| Franklin | 2013-09-11 | H.008008 821-24-0007 |
LA 3201 | Turkey Creek Bridge | Bridge Replacement | $2,500,000 to $5,000,000 | 0.01 | Rabalais, Nick |
| Franklin | 2013-10-23 | H.006109 713-21-0114 |
Parish Line Road Bridge - East | Bridge Replacement | $250,000 to $500,000 | 0.00 | Pentek, Gary | |
| Grant | 2013-06-12 | H.006127 713-22-0121 |
Douglas Road Bridge Over Swafford Creek | Bridge Replacement | $250,000 to $500,000 | 0.00 | Pentek, Gary | |
| Iberia | 2013-06-26 | H.008674 713-23-0002 |
Estis Road Bridge Over Channel L3h | Bridge Replacement | $250,000 to $500,000 | 0.00 | Pentek, Gary | |
| Iberia | 2013-06-30 | H.010614 | Rt 207 (Central Dr):bnsf RR Xing(Iberia) | Upgrade Bnsf RR Signals At Iberia Parish Rt 207 | $0 to $100,000 | 0.00 | Shrewsberry,Bill | |
| Iberia | 2013-08-02 | H.009177 | New Iberia Intersection Safety Improve | Purchase and Install Signs and Solar Beacons | $100,000 to $250,000 | 0.00 | Holm, Rick | |
| Iberia | 2013-08-14 | H.009632 | LA 320 | La 320: La 182 - La 86 | Asphalt Concrete Overlay | $1,000,000 to $2,500,000 | 2.39 | Chenevert, Mark |
| Iberia | 2013-08-28 | H.009467 | LA 671 | Jeanerette Br New Wedge System | Mechanical Repairs | $500,000 to $1,000,000 | 0.06 | Lambert, Jarrett |
| Iberia | 2013-09-03 | H.010666 | Deare Street: Bnsf RR Xing (New Iberia) | Install F/L's & Gates At Deare Street | $100,000 to $250,000 | 0.00 | Shrewsberry,Bill | |
| Iberia | 2013-09-03 | H.010850 | Sign Safety Improvements | Purchase and Install Regulatory & Warning Signs | $0 to $100,000 | 0.00 | Holm, Rick | |
| Iberia | 2013-09-11 | H.002753 397-05-0016 |
LA 89 | Bayou Parc Perdu & Creek Bridges | Bridge Replacement | $1,000,000 to $2,500,000 | 1.64 | Bucci, Mark |
| Iberville | 2013-06-30 | H.009849 | LA 77 | Up (Grosse Tete) La 77 | Install F/L's and Gates | $250,000 to $500,000 | 0.00 | Shrewsberry,Bill |
| Iberville | 2013-06-30 | H.009870 | Up (Grosse Tete) Cedar St. | Install F/L's and Gates | $250,000 to $500,000 | 0.00 | Shrewsberry,Bill | |
| Iberville | 2013-08-05 | H.010175 | Saint Gabriel Trail At the Levee | Construction Of 2,640' Of Levee Trail | $100,000 to $250,000 | 0.00 | Horton, Valerie | |
| Iberville | 2013-09-03 | H.010665 | Up Several RR Xings (Iberville) | Install F/L's & Gates At Hurdle & West Oak Crossings | $0 to $100,000 | 0.00 | Shrewsberry,Bill | |
| Iberville, Pointe Coupee | 2013-08-14 | H.009911 | LA 75, LA 414 | La75 & La 414(N): Thin Asph Conc Overlay | Thin Asphaltic Concrete Overlay | $1,000,000 to $2,500,000 | 7.32 | Ray, Jared |
| Jackson | 2013-06-12 | H.006131 713-25-0106 |
Olive Grove Road Bridges | Bridge Replacement | $500,000 to $1,000,000 | 0.00 | Pentek, Gary | |
| Jackson | 2013-06-12 | H.010502 | LA 146 | La 146: Lincoln Parish Line - La 155 | Surface Treatment | $500,000 to $1,000,000 | 10.05 | Chenevert, Mark |
| Jackson | 2013-06-26 | H.009885 | LA 155, LA 4 | La4 & La155:jackson; Asph. Surf. Treatmt | Surface Treatment | $500,000 to $1,000,000 | 7.54 | Chenevert, Mark |
| Jackson | 2013-07-10 | H.010336 | LA 811 | La 811: La 4 - La 542 | Overlay | $1,000,000 to $2,500,000 | 5.60 | Chenevert, Mark |
| Jackson | 2013-09-11 | H.010423 | US 167 | Us 167 Roadway Flooding 1.5 Mi N La 542 | Addition Of Two Cb's and One Discharge Pipe | $0 to $100,000 | 0.47 | Golz, Sarah |
| Jackson | 2013-09-25 | H.010333 | LA 148 | La 148: La 146 - US 167 | Overlay | $2,500,000 to $5,000,000 | 7.14 | Chenevert, Mark |
| Jefferson | 2013-06-26 | H.009854 | LA 1 | La 1: S. Bank Bayou Rigaud - Cedar St. | Drainage, Widening, Overlay, Striping | $1,000,000 to $2,500,000 | 2.36 | Rojas, Brittany |
| Jefferson | 2013-07-10 | H.009933 | US 90-Z | Macarthur Interchange Completion Ph. 1b | Construct New Entrance Ramp and Bridge Rehabilitation | $30,000,000 to $50,000,000 | 0.75 | Yang, Li |
| Jefferson | 2013-08-14 | H.002260 249-90-0035 |
LA 45 | Goose Bayou Bridge | Bridge Replacement | $2,500,000 to $5,000,000 | 0.40 | Tsai, Loong Shen |
| Jefferson | 2013-08-14 | H.002953 429-02-0030 |
LA 3134 | La 3134: Intracoastal Canal - La 45 | Cold Plane & Overlay | $2,500,000 to $5,000,000 | 6.70 | Chenevert, Mark |
| Jefferson | 2013-08-14 | H.010327 | LA 45 | La 45: Tusa Dr. - Oak Forest | Drainage Structure Additions | $250,000 to $500,000 | 2.14 | Golz, Sarah |
| Jefferson | 2013-09-11 | H.008046 826-03-0016 |
LA 3152 | La 3152 : Clearview Operational Imprv. | Intersection Improvements, Including Additional Turn Lanes | $500,000 to $1,000,000 | 0.65 | Branton, Jennifer |
| Jefferson | 2013-10-09 | H.007177 742-26-0038 |
Ames Blvd (Barataria - Oregon Dr) | Continuous Turn Lane & Drainage Imp | $7,500,000 to $10,000,000 | 0.63 | Riggs, Laura | |
| Jefferson | 2013-10-15 | H.010589 | Bucktown Connector, Ph. 3 | Construction Of Ped-bike Trailhead. | $0 to $100,000 | 0.00 | Horton, Valerie | |
| Jefferson Davis | 2013-06-30 | H.010072 | Bnsf (Jefferson Davis) E. Racca Rd. | Railroad Signalization | $250,000 to $500,000 | 0.00 | Shrewsberry,Bill | |
| Jefferson, Orleans | 2013-05-17 | H.010574 | US 90-Z | Cccd Cctv Camera/Rvd Repairs | Repair Or Removal Of Equipment. | $100,000 to $250,000 | 10.14 | Smith, Erik |
| Jefferson, Orleans | 2013-10-09 | H.010834 | I-10, I-610, I-510 | I-10,I-510,I-610: Pavement Mark Replac I | Replace Pavement Markings In Jeff. and Orleans Parishes | $1,000,000 to $2,500,000 | 43.63 | Colvin, Jody |
| Lafayette | 2013-07-10 | H.003002 450-05-0060 |
I-49, I-10, US 167 | La Dotd Lighting Rehabilitation | Interchange Lighting | $500,000 to $1,000,000 | 3.10 | Domingue, Christopher |
| Lafayette | 2013-09-11 | H.007229 742-28-0003 |
Lafayette Con.Gov. Sr2s Project | Sidewalks. Etc. | $100,000 to $250,000 | 0.00 | Gros, Scott | |
| Lafayette | 2013-09-11 | H.009630 | LA 719 | La 719: La 342 - US 90 | Stabilize Base and Overlay | $5,000,000 to $7,500,000 | 5.26 | Chenevert, Mark |
| Lafayette | 2013-10-10 | H.010575 | Lafayette Urban Bicycle Trails | Construction Of a Ped-bike Trail System. | $100,000 to $250,000 | 0.00 | Horton, Valerie | |
| Lafayette, St. Martin | 2013-10-09 | H.010835 | I-10 | I-10: Pavement Marking Replacement I | Repl Pavement Markings On I-10 In Laf., St. Mart. Parishes | $250,000 to $500,000 | 24.64 | Colvin, Jody |
| Lafourche | 2013-06-20 | H.010818 | LA 1 | La 1: Curve In Larose | Solar Flashing Beacon Lights, Oversized Advanced Curve Warn | $0 to $100,000 | 0.28 | Gisclair, Gary |
| Lafourche | 2013-06-26 | H.006147 713-29-0103 |
Tiger Drive Bridge Over Bayou Lafourche | Bridge Replacement | $1,000,000 to $2,500,000 | 0.00 | Pentek, Gary | |
| Lafourche | 2013-08-14 | H.010169 | LA 307 | Kraemer Lift Bridge Mechanical Repairs | Mechanical Repair | $500,000 to $1,000,000 | 0.05 | Lambert, Jarrett |
| Lafourche | 2013-08-14 | H.010731 | LA 1 | La 1: Jefferson/Lafourche Line - La 3090 | Rehabilitation to Shoulders and Minor Overlay to the Roadway | $2,500,000 to $5,000,000 | 6.31 | Bajewski, Christina |
| Lafourche | 2013-10-09 | H.010738 | LA 3235 | La 3235: Signs and Rumble Stirps | Install Signage, Flashing Beacons, and Rumble Strips | $250,000 to $500,000 | 16.02 | Colvin, Jody |
| Lafourche | 2013-10-11 | H.010578 | Thibodaux Bayou Boardwalk | Construction Of a Ped-bike Trail and Boardwalk. | $100,000 to $250,000 | 0.00 | Horton, Valerie | |
| Lafourche | 2013-10-23 | H.010400 | LA 304, LA 308 | La 304/La 308: Thin Overlay | Cold Plane and Superpave Asphaltic Concrete Overlay | $2,500,000 to $5,000,000 | 9.82 | Chenevert, Mark |
| Lincoln | 2013-06-26 | H.009524 | US 167, LA 150, US 80, US 63 | Us 167: 0.23 Mi S US 80 to N Ruston C/L | Asphalt Overlay Of Concrete Pavement | $1,000,000 to $2,500,000 | 3.18 | Chenevert, Mark |
| Lincoln | 2013-07-15 | H.009169 | Ruston Intersection Safety Improvements | Install Signs and Solar Beacons | $0 to $100,000 | 0.00 | Holm, Rick | |
| Lincoln | 2013-08-28 | H.008155 831-04-0007 |
LA 822 | La 822: La 33 - La 145 | Stabilize and Overlay | $2,500,000 to $5,000,000 | 6.56 | Chenevert, Mark |
| Lincoln | 2013-09-11 | H.009277 | LA 149 | Grambling Sr2s Project | Sidewalk, Crosswalks, Markings Etc. | $250,000 to $500,000 | 0.44 | Gros, Scott |
| Lincoln, Madison, Ouachita, Richland | 2013-09-11 | H.010685 | I-20 | I-20: Dist. 05 Median Cable Barrier | Median Cable Barriers | $15,000,000 to $20,000,000 | 116.09 | Hicks, Melvin |
| Lincoln, Morehouse, Union | 2013-06-12 | H.009883 | LA 552, LA 133, LA 563 | La552; La563; La133; Asph. Surface Treat | Surface Treatment | $1,000,000 to $2,500,000 | 16.40 | Chenevert, Mark |
| Livingston | 2013-06-12 | H.010459 | LA 444 | La 444: La 63 - Gum Swamp Road | Cold Plane, Drainage, Base and Overlay | $1,000,000 to $2,500,000 | 3.95 | Chenevert, Mark |
| Livingston | 2013-09-11 | H.009263 | US 190 | Us 190: Left Turnlane At La 449 | Left Turnlane | $250,000 to $500,000 | 0.21 | Chenevert, Mark |
| Livingston | 2013-09-11 | H.009836 | I-12 | I-12: Walker to 0.5m West Of Satsuma | Widening I-12 From Walker to Satsuma to 6 Lanes | $20,000,000 to $30,000,000 | 3.58 | Tsai, Loong Shen |
| Livingston | 2013-10-09 | H.008193 832-32-0015 |
LA 3002 | La 1034 - US 190 | Cold Plane. Patch and Olay | $500,000 to $1,000,000 | 2.54 | Chenevert, Mark |
| Livingston | 2013-10-09 | H.009179 | Wax Road | Overlay and Widening | $1,000,000 to $2,500,000 | 1.76 | Riggs, Laura | |
| Livingston | 2013-10-09 | H.009180 | Plantation Rd / Enterprise Rd | Overlay and Widening | $500,000 to $1,000,000 | 1.78 | Riggs, Laura | |
| Livingston | 2013-10-09 | H.010638 | River Rd: Government St - Centerville St | Minor Widening and Overlay, Some Pavement Patching Required | $250,000 to $500,000 | 0.52 | Riggs, Laura | |
| Madison | 2013-07-10 | H.010603 | I-20 | I-20 Mr Br Mod For Tran Realign Pier E-2 | Pier E2 to Modification to Accomodate Lateral Movement | $2,500,000 to $5,000,000 | 2.07 | D'andrea, Artur |
| Madison, Ouachita, Richland | 2013-10-09 | H.010838 | I-20 | I-20: Pavement Marking Replacement I | Repl Pave Marking On I-20 In Oua, Rich, and Madison Parish | $500,000 to $1,000,000 | 29.25 | Colvin, Jody |
| Madison, Richland | 2013-10-09 | H.003332 451-07-0052 |
I-20 | I-20: Richland/Madison Parish Ramp Rehab | Ramp Rehab (Richland Parish and Madison Parish) | $7,500,000 to $10,000,000 | 60.36 | Thomas, Ben |
| Morehouse | 2013-10-09 | H.010527 | LA 590 | La 590: Elvin Rd. - La 591 | Overylay | $250,000 to $500,000 | 2.64 | Chenevert, Mark |
| Natchitoches | 2013-06-12 | H.009329 | I-49 | I-49: Kisatchie Bayou Scour Mitigation | Repair Slope Failure & Apply Abutment Protection From Scour | $250,000 to $500,000 | 0.25 | Cavalier, Stephanie |
| Natchitoches | 2013-08-05 | H.009174 | Natchitoches Intersection Safety Improve | Purchase and Install Signs and Solar Beacons | $0 to $100,000 | 0.00 | Holm, Rick | |
| Natchitoches | 2013-10-17 | H.010594 | Louisiana Trail: Goldonna to Chestnut | Construction Of a Multi-use Trail. | $100,000 to $250,000 | 0.00 | Horton, Valerie | |
| Orleans | 2013-05-22 | H.009657 | LA 611-9 | La 611-9:metairie Rd;jefferson P/L-i-10 | Cold Plane and Overlay and Concrete Pavement Rehab | $500,000 to $1,000,000 | 0.68 | Chenevert, Mark |
| Orleans | 2013-06-12 | H.009342 | M/V Thomas Jefferson Re-propulsion | Change Out Propulsion System. Upgrade Engines, Generators | $2,500,000 to $5,000,000 | 0.00 | Rau, Gerard | |
| Orleans | 2013-06-12 | H.010647 | LA 428 | La 428: Lb Landry Ave- Holiday Dr | Overlay and Striping | $1,000,000 to $2,500,000 | 1.82 | Rojas, Brittany |
| Orleans | 2013-06-26 | H.005889 704-92-0017 |
US 90-Z | Cccd-us 90bus Sign Installations | Overhead Signing On US 90 Bus | $100,000 to $250,000 | 0.24 | Courtier, Kay |
| Orleans | 2013-07-10 | H.003181 450-90-0245 |
I-10 | I-10 Wb Over Julia Street Girder Rehabil | Replace and Repair Damaged Steel and Connection Plates | $500,000 to $1,000,000 | 1.00 | Bucci, Mark |
| Orleans | 2013-07-10 | H.009699 | Ada Access Ramps In Cbd | Sidewalk Improvements | $250,000 to $500,000 | 0.00 | Riggs, Laura | |
| Orleans | 2013-08-14 | H.003182 450-90-0246 |
I-10 | Ihnc and Algiers Cutoff Bridge Rehab | Finger Joints,Rocker Bearings & Deck Overlay | $5,000,000 to $7,500,000 | 1.27 | Kemp, Kelly |
| Orleans | 2013-08-14 | H.006566 737-36-0015 |
Arise Academy Srts | Sidewalks/Signs/Etc. | $100,000 to $250,000 | 0.00 | Gros, Scott | |
| Orleans | 2013-09-11 | H.006568 737-36-0017 |
Washington Ave Pedestrian Crossing | Constr Bike/Pedest X-ing @ Xavier U | $1,000,000 to $2,500,000 | 0.00 | Rabalais, Nick | |
| Orleans | 2013-09-11 | H.010789 | I-10 | I-10: Irish Bayou Bridge Emergency Rep | Scour Repair and Erosion Protection | $500,000 to $1,000,000 | 0.08 | Branton, Jennifer |
| Orleans | 2013-09-25 | H.009987 | Submerged Rds.-phase B (Group 34) | Overlay, Patching, Striping, Improving Ada Ramps | $2,500,000 to $5,000,000 | 0.00 | Burst, Jeffery | |
| Orleans | 2013-10-09 | H.007265 742-36-0126 |
St Charles Ave (La Ave-calliope St) | Overlay | $2,500,000 to $5,000,000 | 0.00 | Riggs, Laura | |
| Orleans | 2013-10-09 | H.007277 742-36-0142 |
Lake Forest Boulevard | Minor Widening | $250,000 to $500,000 | 0.00 | Branton, Jennifer | |
| Orleans | 2013-10-09 | H.010712 | I-10 | I-10: Median Cable Barrier: Orleans Par | Median Cable Barrier | $1,000,000 to $2,500,000 | 24.26 | Branton, Jennifer |
| Orleans | 2013-10-10 | H.010576 | Jefferson Davis Trails | Construction Of a Ped-bike Trail System. | $100,000 to $250,000 | 0.00 | Horton, Valerie | |
| Orleans | 2013-10-10 | H.010577 | Couterie Urban Forest Trailhead | Construction Of a Ped-bike Trailhead and Boardwalk Trail. | $100,000 to $250,000 | 0.00 | Horton, Valerie | |
| Ouachita | 2013-06-03 | H.010115 | Jack Hayes Elem. Srts Non-infrastructure | Purchases, Incentives, Bicycle Racks, Training. | $0 to $100,000 | 0.00 | Babin, Dennis | |
| Ouachita | 2013-06-12 | H.009537 | US 80 | Us 80: Rifle Range Road to La 594 | Overlay | $1,000,000 to $2,500,000 | 2.14 | Chenevert, Mark |
| Ouachita | 2013-06-26 | H.009480 | I-20 | I-20 Ouachita River Bridge | Bridge Rehabilitation | $20,000,000 to $30,000,000 | 1.73 | Yap, Kian |
| Ouachita | 2013-08-14 | H.000169 002-01-0047 |
US 80 | Union Pacific Railroad Bridge At Sicard | Bridge Replacement | $7,500,000 to $10,000,000 | 0.40 | Rabalais, Nick |
| Ouachita | 2013-08-14 | H.007065 742-06-0050 |
US 165 | Finks Hideaway (Us 165-holland) Ph1 | Widen to 5 Lanes | $7,500,000 to $10,000,000 | 0.12 | Borne, Fred |
| Ouachita | 2013-09-11 | H.006576 737-37-0011 |
Monroe ITS Phase 1 | Its/Emergency Operations | $1,000,000 to $2,500,000 | 0.00 | Delaney, Elizabeth | |
| Ouachita | 2013-09-11 | H.009999 | US 165, LA 594 | La 594: Turn Ln @ US 165 Service Rd. | Widening and Realigning US 165 Serv Rd Across Kcs & La 594 | $2,500,000 to $5,000,000 | 0.36 | Hicks, Melvin |
| Ouachita | 2013-09-11 | H.010431 | LA 34 | La 34: Turn Lane @ Old Natchitoches Rd | Left Turn Lane Added to La 34 Onto Natchitoches St. | $500,000 to $1,000,000 | 0.05 | Deville, Jacques |
| Ouachita | 2013-10-11 | H.010582 | Louisiana Delta Community College Trail | Construction Of a Ped Nature Trail. | $0 to $100,000 | 0.00 | Horton, Valerie | |
| Plaquemines | 2013-08-14 | H.010326 | LA 23 | La 23: Ave. B - Apricot St. | Modification Of Cb-06 and Cb-07 Tops As Per Ladotd Standard | $100,000 to $250,000 | 1.19 | Golz, Sarah |
| Pointe Coupee | 2013-05-22 | H.008248 839-24-0005 |
LA 1, LA 1-Y | La 1: Hospital Road & Wb Left Turn Ln. | Widen-3lane Cont 2-way Lt Turn Lane | $2,500,000 to $5,000,000 | 2.20 | Beauvais, Hewitt |
| Pointe Coupee | 2013-06-12 | H.009394 | LA 77 | La 77: Drainage Improvements | Raise Finished Grade and Overlay | $0 to $100,000 | 0.00 | Golz, Sarah |
| Pointe Coupee | 2013-06-30 | H.010089 | Major Parkway: Kcs RR Xing (New Roads) | Railroad Signalization | $250,000 to $500,000 | 0.00 | Shrewsberry,Bill | |
| Pointe Coupee | 2013-07-30 | H.010742 | LA 10, LA 975 | Miss River Flood - Material Acquisition | Purchase, Transport and Spread Aggregate Material | $100,000 to $250,000 | 10.60 | Vosburg, Chad |
| Pointe Coupee | 2013-08-15 | H.010745 | LA 1 | La 1: Guard Rail At Simmesport Br | Install Guardrail At Simmesport Br. | $0 to $100,000 | 0.09 | Beauvais, Hewitt |
| Pointe Coupee, West Baton Rouge | 2013-05-22 | H.010436 | LA 982, LA 417 | La 417 & La 982: Stabilize & Overlay | Stabilize & Overlay | $5,000,000 to $7,500,000 | 10.88 | Chenevert, Mark |
| Pointe Coupee, West Baton Rouge | 2013-10-09 | H.010435 | LA 413, LA 411 | La 411 & La 413: Patch,Stabilize,Overlay | Patch, Stabilize, & Overlay | $7,500,000 to $10,000,000 | 14.46 | Chenevert, Mark |
| Rapides | 2013-06-12 | H.002670 368-02-0006 |
LA 488 | La 488:jct. La 112 - Valentine Lake Road | Ctb & Overlay | $2,500,000 to $5,000,000 | 6.33 | Chenevert, Mark |
| Rapides | 2013-08-14 | H.010372 | LA 457 | La 457:jct US 71-239' N Of Tiger Lake Rd | Ctb & Overlay | $1,000,000 to $2,500,000 | 5.45 | Chenevert, Mark |
| Rapides | 2013-10-09 | H.010172 | City Of Alexandria Sidewalk Improvements | Sidewalk Improvements | $1,000,000 to $2,500,000 | 0.00 | Hanks, Anna | |
| Rapides | 2013-10-23 | H.010373 | LA 497 | La 497: 7th Ave - Jct La 112 | Stabize Base and Overlay | $2,500,000 to $5,000,000 | 5.70 | Chenevert, Mark |
| Red River | 2013-06-12 | H.010248 | US 71, US 84 | Roadway Drainage Improve - US 71 @ US 84 | Drainage Improvements | $500,000 to $1,000,000 | 0.46 | Golz, Sarah |
| Red River | 2013-10-09 | H.009402 | US 371 | Rdwy Drainage Imp.-us 71 @ US 371 Ph Iii | Subsurface Drainage and Outfall Channel Improvements | $500,000 to $1,000,000 | 0.42 | Golz, Sarah |
| Red River | 2013-10-09 | H.009515 | LA 786 | La 786: US 371 to La 507 | Mill and Overlay | $1,000,000 to $2,500,000 | 5.14 | Chenevert, Mark |
| Richland | 2013-06-12 | H.009390 | US 80 | Us 80: Drainage Improvements @ La 852 | Drainage Improvements | $100,000 to $250,000 | 0.03 | Golz, Sarah |
| Sabine | 2013-06-12 | H.009490 | LA 118 | La 118: Mt Carmel-peason Ridge Artillary | Stabilize & Overlay and Patch & Overlay | $2,500,000 to $5,000,000 | 8.63 | Chenevert, Mark |
| Sabine | 2013-07-10 | H.009540 | LA 1218 | La 1218: US 171 - La 191 | Patch & Overlay | $500,000 to $1,000,000 | 2.81 | Chenevert, Mark |
| Sabine | 2013-09-25 | H.010370 | LA 3118 | La 3118: Sw Jct La 6 - Ne Jct La 6 | Patch & Overlay | $500,000 to $1,000,000 | 1.26 | Chenevert, Mark |
| Sabine | 2013-09-30 | H.010711 | LA 482 | La 482: Kcs RR Xing (Zwolle) | Upgrade RR Signals to Allow For Traffic Signal Preemption | $0 to $100,000 | 0.01 | Shrewsberry,Bill |
| Sabine | 2013-10-31 | H.010696 | Brown & Gandy: Kcs RR Xings (Sabine) | Install F/L's & Gates At Brown and Gandy Xings | $250,000 to $500,000 | 0.00 | Shrewsberry,Bill | |
| St. Bernard | 2013-08-14 | H.010401 | LA 46, LA 625, LA 624 | La 46, La 624 & La 625:thin Overlay | Overlay | $1,000,000 to $2,500,000 | 7.43 | Chenevert, Mark |
| St. Bernard | 2013-09-25 | H.007331 742-44-0006 |
Packenham Dr (La46 - La39) | Reconstruct | $2,500,000 to $5,000,000 | 0.00 | Riggs, Laura | |
| St. Bernard | 2013-10-10 | H.010586 | St Bernard P Mississippi River Trail Ph3 | Construction Of a Ped-bike Trail. | $500,000 to $1,000,000 | 0.00 | Horton, Valerie | |
| St. Charles | 2013-06-12 | H.009163 | LA 48 | La 48: Wesco St - US 61 | Thin Asphaltic Concrete Overlay | $500,000 to $1,000,000 | 1.83 | Gaudet, Corey |
| St. Charles | 2013-06-26 | H.010584 | I-310 | Replacing Guide Signs On I-310 | Replace Guide Sign On I-310 | $1,000,000 to $2,500,000 | 11.63 | Courtier, Kay |
| St. Charles | 2013-07-10 | H.009656 | I-310 | I-310 Service Rd: La 50 - Dead End | Cold Plane and Overlay | $100,000 to $250,000 | 0.00 | Thomas, Ben |
| St. Charles | 2013-10-09 | H.009563 | US 90 | Us 90:right Turn Lane @ La 306 | Install Turnlane On Eb US 90 @ La 306 | $100,000 to $250,000 | 0.15 | Deville, Jacques |
| St. Helena | 2013-10-01 | H.010623 | LA 10-S, LA 1042 | La1042:la37-la43 & La10s:la43-cslm 0.54 | Asphaltic Concrete Pavement Overlay and Striping | $250,000 to $500,000 | 0.76 | Sharp, Larry W. |
| St. Helena | 2013-10-22 | H.010627 | LA 3126 | La 3126: La 10 - End Of Control | Clearing & Grubbing, Asphaltic Concrete Pavement, Base Cours | $250,000 to $500,000 | 0.39 | Sharp, Larry W. |
| St. James | 2013-06-12 | H.002933 426-31-0016 |
LA 3125 | La 3125: La 70 - La 3214 | Cold Plane & Overlay Asphaltic Pavement | $2,500,000 to $5,000,000 | 4.98 | Chenevert, Mark |
| St. James | 2013-08-01 | H.010552 | St. James East Bank Levee Trail, Ph 2 | 8' Wide X 0.4 Mi Long Asphalt Trail On Miss River Levee Toe | $100,000 to $250,000 | 0.00 | Horton, Valerie | |
| St. John Baptist | 2013-05-22 | H.010635 | I-10 | I-10 Raising Roadway | Drainage | $1,000,000 to $2,500,000 | 0.33 | Golz, Sarah |
| St. John Baptist | 2013-06-26 | H.000327 007-04-0054 |
US 61 | Us 61 @ Belle Terre Blvd. | Traffic Flow Improvements | $1,000,000 to $2,500,000 | 0.35 | Riggs, Laura |
| St. John Baptist | 2013-07-31 | H.010185 | Garyville Mill Pond &northern Trail Ph 1 | Construction Of 8' Wide By 2,800'long Asphalt Ped Bike Trail | $100,000 to $250,000 | 0.00 | Horton, Valerie | |
| St. Landry | 2013-06-26 | H.009468 | US 190 | Us 190 Krotz Spgs Atchaf Br Clean&paint | Cleaning and Painting | $10,000,000 to $15,000,000 | 0.65 | Tullier, Danny |
| St. Landry | 2013-08-14 | H.010265 | US 190 | Us 190: Turnout Improvements At La 104 | Construct Right Turn Lane | $100,000 to $250,000 | 0.20 | Deville, Jacques |
| St. Landry | 2013-10-09 | H.010217 | LA 105 | La 105: La 3173 - US 190 | Stabilize Base & Overlay; Asphalt Overlay | $250,000 to $500,000 | 0.78 | Chenevert, Mark |
| St. Landry | 2013-10-15 | H.010587 | Walking Trail At Opelousas Sports Park | Construction Of a Ped Trail In a Public Park. | $100,000 to $250,000 | 0.00 | Horton, Valerie | |
| St. Landry | 2013-10-17 | H.010593 | Bayou Teche Paddle Trail | Construction Of a Paddle and Atv Trail. | $100,000 to $250,000 | 0.00 | Horton, Valerie | |
| St. Landry | 2013-10-23 | H.009704 | Manuel St At S East St and E Dean St | Guard Rail Installation | $0 to $100,000 | 0.00 | Holm, Rick | |
| St. Martin | 2013-05-22 | H.006292 713-50-0109 |
Lion Castille Road Bridge Over Bayou Por | Bridge Replacement | $250,000 to $500,000 | 0.00 | Pentek, Gary | |
| St. Martin | 2013-08-14 | H.010646 | I-10 | Girder Replacement and Repair | Replace Exterior Girder and Repair Misc. Damage to Structure | $250,000 to $500,000 | 0.01 | Thomas, Holly |
| St. Martin | 2013-09-11 | H.009946 | LA 352 | La 352:herman Dupuis Rd - Coffee Town Rd | Stabilize Base & Overlay | $2,500,000 to $5,000,000 | 4.49 | Chenevert, Mark |
| St. Mary | 2013-10-15 | H.010588 | Atchafalaya River Levee Berwick Trail | Construction Of a Ped-bike Trail. | $100,000 to $250,000 | 0.00 | Horton, Valerie | |
| St. Tammany | 2013-05-22 | H.003641 690-01-0001 |
I-59 Slidell (Pearl River) Rest Area Imp | Parking. Lighting and Pavilions | $2,500,000 to $5,000,000 | 0.00 | Guinn, Michael S | |
| St. Tammany | 2013-06-12 | H.000492 013-11-0039 |
US 190 | Us 190 (I-12 - La 22) | Overlay | $7,500,000 to $10,000,000 | 2.93 | Hanks, Anna |
| St. Tammany | 2013-06-12 | H.009125 | I-12 | I-12 Eb Exit Ramp Extension At US 190 | Exit Ramp Extension | $1,000,000 to $2,500,000 | 0.47 | Sharp, Larry W. |
| St. Tammany | 2013-06-26 | H.005973 706-99-0005 |
Lake Ponchartrain Causeway (Realignment/ | Bridge Rehab | $500,000 to $1,000,000 | 24.09 | Picard, Toby | |
| St. Tammany | 2013-07-10 | H.010643 | US 190 | Us 190: Paved Shoulders/Guardrail Aprons | Us 190: Paved Shoulders/Guardrail Aprons | $250,000 to $500,000 | 1.00 | Sharp, Larry W. |
| St. Tammany | 2013-08-28 | H.006298 713-52-0105 |
Oak Street Bridge Over Gum Bayou | Bridge Replacement | $500,000 to $1,000,000 | 0.00 | Pentek, Gary | |
| St. Tammany | 2013-08-28 | H.006299 713-52-0106 |
Grande Avenue Bridge Over Cypress Bayou | Bridge Replacement | $250,000 to $500,000 | 0.00 | Pentek, Gary | |
| St. Tammany | 2013-09-11 | H.009325 | South Channel Fender Repair | Repair Damage and Deterioration to Fender | $1,000,000 to $2,500,000 | 0.00 | Fletcher, Curtis | |
| St. Tammany | 2013-09-25 | H.010618 | LA 433 | Bayou Bonfouca Swing Bridge Perm Rep | Remove and Inspect Center Pivot Bearing Assembly, Repair | $100,000 to $250,000 | 0.06 | Berner, Darrick |
| St. Tammany | 2013-09-25 | H.010619 | US 90 | East Pearl River Swing Bridge Repairs | Rem & Insp Center Pivot Bearing Assembly, Repair If Necessar | $100,000 to $250,000 | 0.18 | Berner, Darrick |
| St. Tammany | 2013-09-25 | H.010709 | LA 22 | Madisonville Swing Bridge Perm Repair | Bridge Reconditioning | $250,000 to $500,000 | 0.06 | Berner, Darrick |
| St. Tammany | 2013-10-09 | H.001340 059-01-0028 |
LA 21 | La 21 Widening (Bootlegger - 11th) | Widening | $10,000,000 to $15,000,000 | 1.46 | Kendrick, Brian |
| St. Tammany | 2013-10-09 | H.003107 450-18-0108 |
I-10, I-59, I-12 | I-10: French Branch Br -w.Pearl River Br | Pavement Replacement | $30,000,000 to $50,000,000 | 4.47 | Thomas, Ben |
| St. Tammany | 2013-10-11 | H.010580 | Bogue Chitto Nwr Trails | Construction Of a Ped Nature Trail. | $0 to $100,000 | 0.00 | Horton, Valerie | |
| St. Tammany, Tangipahoa | 2013-10-09 | H.010790 | I-55, I-12 | I-55 Cn R/R & I-12 US 51 Slope Failure | Embankment and Abutment Repair | $1,000,000 to $2,500,000 | 0.47 | Brown, Jeff |
| Statewide | 2013-06-30 | H.009884 | Nogc (Statewide) | Relocating Led Crossbuck Assemblies | $100,000 to $250,000 | 0.00 | Shrewsberry,Bill | |
| Statewide | 2013-07-10 | H.010721 | Construct New Landing Barges | Construct and Deliver New Landing Barges | $1,000,000 to $2,500,000 | 0.00 | Reed, Kevin | |
| Statewide | 2013-07-30 | H.010183 | Pharr Estates Trail (Phase I) | Construction Of 850' Of Bicycle Trail | $100,000 to $250,000 | 0.00 | Horton, Valerie | |
| Tangipahoa | 2013-06-04 | H.009894 | LA 1063 | La 1063: La 442 to US 51 | Chip Seal | $100,000 to $250,000 | 6.59 | Chenevert, Mark |
| Tangipahoa | 2013-06-04 | H.009895 | LA 1050 | La 1050: La 1051 to La 38 | Chip Seal | $100,000 to $250,000 | 4.07 | Chenevert, Mark |
| Tangipahoa | 2013-06-12 | H.009392 | US 51, LA 40 | La 40 and US 51 Drainage Improvements | Drainage Improvements | $100,000 to $250,000 | 0.45 | Golz, Sarah |
| Tangipahoa | 2013-08-14 | H.010087 | US 51-X, I-12 | Us 51 B @ I-12:clear & Grub(Roundabouts) | Clearing & Grubbing | $0 to $100,000 | 0.78 | Olivier, Nicholas |
| Tangipahoa | 2013-09-25 | H.010737 | Dotd District 62 Wind Retofit Project | Install Storm Protection Screens and Related Work | $0 to $100,000 | 0.00 | Berner, Darrick | |
| Tangipahoa | 2013-10-09 | H.000482 013-09-0051 |
US 190 | Us 190: La 443 - St. Tammany Line | Cold Plane, Patch, and Overlay | $7,500,000 to $10,000,000 | 12.15 | Chenevert, Mark |
| Tangipahoa | 2013-10-09 | H.010386 | US 51 | Us 51: N Jct La 10 - Mississippi S/L | Cold Plane & Overlay | $2,500,000 to $5,000,000 | 12.60 | Chenevert, Mark |
| Terrebonne | 2013-06-12 | H.002232 246-01-0054 |
LA 57 | Industrial Blvd. - Thompson Rd. | Widen to 5 Lane | $7,500,000 to $10,000,000 | 1.80 | Winchester, Chad |
| Terrebonne | 2013-06-26 | H.009564 | LA 24, LA 3040 | La 24 & La 3040: Drainage & Rt Turn Lane | Install Right Turn Lane | $250,000 to $500,000 | 0.19 | Deville, Jacques |
| Terrebonne | 2013-09-11 | H.007350 742-55-0002 |
Hollywood Rd. Widening | Widen to 4 Lanes | $5,000,000 to $7,500,000 | 0.00 | Borne, Fred | |
| Terrebonne | 2013-09-11 | H.010398 | LA 57 | La 57:la 3011-la 56 | Superpave Asphaltic Concrete Overlay | $1,000,000 to $2,500,000 | 7.84 | Chenevert, Mark |
| Terrebonne | 2013-10-11 | H.010579 | Westside Bike Trail Route | Construction Of a Bike Trail. | $100,000 to $250,000 | 0.00 | Horton, Valerie | |
| Union | 2013-06-26 | H.006323 713-56-0109 |
Dean Haile Road Bridge Over Finch Bayou | Bridge Replacement | $250,000 to $500,000 | 0.00 | Pentek, Gary | |
| Vermilion | 2013-06-26 | H.009469 | LA 14 | Old Abbeville Br Wire Rope Replacement | Mechanical Repair | $250,000 to $500,000 | 0.05 | Lambert, Jarrett |
| Vermilion | 2013-08-14 | H.002132 212-01-0008 |
LA 91 | Maree Michel and Creek Bridges | Bridge Replacement | $1,000,000 to $2,500,000 | 1.51 | Olivier, Nicholas |
| Vermilion | 2013-09-11 | H.008434 857-02-0006 |
LA 332 | Maree Michel Canal Bridge | Bridge Replacement | $500,000 to $1,000,000 | 0.40 | Delatte, Brian |
| Vernon | 2013-06-03 | H.010678 | Barham Rd: Kcs RR Xing (Vernon) | Install F/L's and Gates | $250,000 to $500,000 | 0.00 | Shrewsberry,Bill | |
| Vernon | 2013-06-12 | H.009560 | LA 463 | La 463: 5 Miles N Of La 10-rapides | Ctb and Overlay | $2,500,000 to $5,000,000 | 8.30 | Chenevert, Mark |
| Vernon | 2013-06-12 | H.010272 | LA 8 | La 8: Median Cable Barrier @ La 117 | Installation Of Cable Barrier Within Median Of La 8/La 28 | $100,000 to $250,000 | 0.63 | Mathews, Larry |
| Vernon | 2013-06-30 | H.010098 | Kcs (Vernon) Several RR X-ing Vernon Par | Railroad Signalization | $1,000,000 to $2,500,000 | 0.00 | Shrewsberry,Bill | |
| Vernon | 2013-08-14 | H.001872 134-01-0013 |
LA 8 | Calcasieu River & Creek Bridges | Bridge Replacement | $15,000,000 to $20,000,000 | 5.95 | Yang, Li |
| Vernon | 2013-10-09 | H.000995 029-04-0025 |
LA 121 | La 121 Bridges Near Hineston | Bridge Replacement | $7,500,000 to $10,000,000 | 15.78 | Rabalais, Nick |
| Vernon | 2013-10-09 | H.010264 | US 171 | Us 171: Nb @ La 1213 Cross Drain Replace | Cross Drain Replacement | $100,000 to $250,000 | 0.01 | Golz, Sarah |
| Washington | 2013-07-10 | H.010173 | LA 439 | La 439: H. Mizell Rd. - La 60 | Asphalt Concrete Overlay Over Cement Treated Base Course | $2,500,000 to $5,000,000 | 5.60 | Chenevert, Mark |
| Webster | 2013-06-26 | H.001688 087-02-0015 |
LA 2 | Indian Creek and Thorny Branch Brdgs. | Bridge Replacement | $2,500,000 to $5,000,000 | 0.66 | Yang, Li |
| Webster | 2013-06-26 | H.010252 | I-20 | I-20: Tree Removal In Webster Parish | Tree Removal Along I-20 In Webster Parish | $250,000 to $500,000 | 16.06 | Baugh, Sam |
| Webster | 2013-07-10 | H.001685 086-30-0019 |
LA 803-1 | La 803-1: Intersection Improvements | Removal Of Railroad Crossing and Geometric Improvements | $100,000 to $250,000 | 0.03 | Deville, Jacques |
| West Baton Rouge | 2013-10-09 | H.010654 | LA 415 | La 415:i-10 to Approximately 0.41m North | Pavement Rehabilitation | $500,000 to $1,000,000 | 0.40 | Riggs, Laura |
| West Baton Rouge | 2013-10-09 | H.010656 | LA 1, LA 76 | La 1 @ La 76 Intersection Improvements | Turn Lanes | $250,000 to $500,000 | 0.00 | Riggs, Laura |
| West Carroll | 2013-06-12 | H.006368 713-62-0009 |
Roundhill Road Bridge Over Drain to Cole | Bridge Replacement | $500,000 to $1,000,000 | 0.00 | Pentek, Gary | |
| West Carroll | 2013-06-12 | H.009526 | LA 585 | La 585: La 2 to Parish Road | Base, Overlay and Ast | $1,000,000 to $2,500,000 | 6.81 | Chenevert, Mark |
| West Carroll | 2013-10-23 | H.010338 | LA 582 | La 582: La 2 - La 17 | Overlay | $1,000,000 to $2,500,000 | 5.75 | Chenevert, Mark |
| Winn | 2013-06-26 | H.006372 713-64-0108 |
Carter Crossing Bridge Over Dugdemona Ri | Bridge Replacement | $1,000,000 to $2,500,000 | 0.00 | Pentek, Gary | |
| Winn | 2013-08-14 | H.001844 123-04-0020 |
LA 34 | Iatt Creek & Redland Creek Bridges | Bridge Replacement | $2,500,000 to $5,000,000 | 0.81 | Delatte, Brian |
| Winn | 2013-08-14 | H.008482 864-09-0007 |
LA 1236 | La 1236 Bridges Near Dodson | Bridge Replacement (4 Bridges) | $2,500,000 to $5,000,000 | 4.47 | Musa, Elnur |