Projects to be Let in the Next 6 Months - By Project Number
PLEASE NOTE:
Projects TENTATIVELY scheduled to be let within the next 6 months. The Letting Dates are contingent upon availability of funds and completion of all pre-construction activities.
| Parish | Letting Date |
Project | Route | Project Name | Type Improvement | Estimated Cost Range |
Length (miles) |
Project Manager | Util Clear Date |
|---|---|---|---|---|---|---|---|---|---|
| Bossier | Dec 2008 | 001-03-0085 | US 80 | Benton Rd. - Old Minden Rd. | Cp & Overlay; Whitetop @ Airline | $1,000,000 to $2,500,000 | 2.51 | Baugh, Sam | |
| Bienville | Nov 2008 | 001-06-0057 | US 80 | E.Jct La 154 - W. Jct La 154 | Minor Overlay | $0 to $100,000 | 0.12 | Broadbent, Ronald | |
| Lincoln | Feb 2009 | 001-08-0036 | US 80 | Ruston Downtown Dist.Revitalization | Sidewalks/Bike Paths | $1,000,000 to $2,500,000 | 0.04 | Horton, Valerie | |
| Richland | Mar 2009 | 002-02-0033 | US 80 | Us 80 At Start (Cross Drain Site) | Cross Drain Pipe Replacement | $0 to $100,000 | 0.01 | Lee, Steven | |
| Madison | Dec 2008 | 002-05-0031 | US 80 | La 602 - La 3218 | Patch, Mill and Overlay | $2,500,000 to $5,000,000 | 3.71 | Colquette, Paul | |
| Jefferson | Dec 2008 | 005-10-0038 | US 90 | Us 90 Turn Lane At Homeplace Road | Add a Turn Lane Into Subdivision | $250,000 to $500,000 | 0.50 | Monzon, John | |
| St. Tammany | Apr 2009 | 006-07-0046 | US 90 | Middle Middle Pearl River Scour Rep | Scour Repair Piers 2 & 3 | $500,000 to $1,000,000 | 0.10 | Guidry, Chris | |
| Rapides | Dec 2008 | 008-09-0057 | US 71 | Us 71 Turn Lane Extension | Turn Lane Extension @ Sugarhouse Rd | $100,000 to $250,000 | 0.01 | Choate, Rodney | |
| Bossier | Jan 2009 | 010-06-0067 | US 71 | La 154 - La 612 | Chip Seal | $100,000 to $250,000 | 7.90 | Broadbent, Ronald | |
| Bossier | Jan 2009 | 010-30-0030 | LA 72 | La 72 West Bound Right Turn Lane | Right Turn Lane | $100,000 to $250,000 | 0.01 | Baugh, Sam | May 2008 |
| Tangipahoa | Mar 2009 | 013-08-0041 | US 190 | Us 190 Drainage Improvements | Drainage Improvements | $500,000 to $1,000,000 | 0.01 | Nilforoushan, Mehdi | |
| Ouachita | Apr 2009 | 015-31-0051 | US 165 | Us 165 Over Various Crossings | Bridge Deck Joint Maint./Repair | $1,000,000 to $2,500,000 | 6.54 | Colquette, Paul | |
| Morehouse | Mar 2009 | 016-05-0030 | US 165 | Mer Rouge - Bonita | Asphalt Surface Treatment | $250,000 to $500,000 | 6.50 | Colquette, Paul | |
| West Feliciana | Mar 2009 | 019-05-0036 | US 61 | Us 61 South Of La 421 | Remove Crossover | $0 to $100,000 | 0.06 | Drake, Bill | |
| DeSoto | Jan 2009 | 021-03-0038 | US 84 | Lm 2.30 - Red River Parish Line | Chip Seal | $250,000 to $500,000 | 9.97 | Broadbent, Ronald | |
| Catahoula | Nov 2008 | 022-06-0039 | US 84 | Jct. La 927w - Jct. La 124 | Widen to Four Lanes | $5,000,000 to $7,500,000 | 0.65 | Guest, Debra | Oct 2008 |
| Beauregard | Jan 2009 | 028-02-0024 | US 190 | East Sabine River Bridge - La 111 | Chip Seal Single | $250,000 to $500,000 | 9.90 | Broadbent, Ronald | |
| Washington | Nov 2008 | 030-03-0020 | LA 21 | La 21 At 6th St. | Intersection Improvements | $250,000 to $500,000 | 0.01 | Schilling, Allison | |
| Beauregard | Nov 2008 | 031-09-0028 | LA 27 | At&sf RR O'pass Removal&pav't Rehab | Asphalt Pavement Rehab | $7,500,000 to $10,000,000 | 5.46 | Lacombe, Jason | May 2005 |
| Natchitoches | Mar 2009 | 034-06-0046 | LA 6 | Red River @ Grand Ecore Bridge | Redecking/Deck Rehabilitation | $15,000,000 to $20,000,000 | 0.36 | Nakhleh, Jenan | |
| Sabine | Dec 2008 | 035-01-0016 | LA 175 | La 175 Curve Realignment | Curve Realignment | $1,000,000 to $2,500,000 | 0.01 | Borne, Fred | Oct 2008 |
| Caldwell | Mar 2009 | 036-01-0023 | LA 4 | Braxton Lane - Franklin Ph Line | Stabilize,Overlay,Spot Repairs | $1,000,000 to $2,500,000 | 4.85 | Mason, Ken | |
| Tensas | Dec 2008 | 036-05-0031 | LA 128 | La 4 - 2.9 Mi. South Of La 4 | Stabilize and Overlay | $1,000,000 to $2,500,000 | 2.90 | Mason, Ken | |
| Morehouse | Mar 2009 | 037-01-0023 | LA 2 | Mer Rouge - East | Asphalt Surface Treatment | $250,000 to $500,000 | 6.01 | Colquette, Paul | |
| Orleans | Feb 2009 | 046-31-0053 | LA 39 | Judge Seeber Bridge Repairs | Movable Br. Wire Ropes & Mech.Rep. | $1,000,000 to $2,500,000 | 0.01 | Harter, John | |
| St. Bernard | Jan 2009 | 046-32-0037 | LA 39 | Judge Perez (Rowley - Paris Rd.) | Patch and Overlay | $1,000,000 to $2,500,000 | 2.21 | Branton, Jennifer | |
| West Carroll | Dec 2008 | 051-07-0020 | LA 17 | S.Oak Grove C.L. - La 2 | Mill and Overlay | $250,000 to $500,000 | 0.60 | Colquette, Paul | |
| West Carroll | Dec 2008 | 051-08-0023 | LA 17 | La 2 - N. Oak Grove C.L. | Mill and Overlay | $250,000 to $500,000 | 0.65 | Colquette, Paul | |
| Caddo | Nov 2008 | 053-09-0069 | LA 1 | La 1 E.Front Rd (Lm 7.57 - Lm 8.15) | Minor Overlay | $100,000 to $250,000 | 0.58 | Broadbent, Ronald | |
| St. Martin | Nov 2008 | 056-04-0029 | LA 336 | Breaux Bridge Repairs | Movable Bridge Replace Wire Ropes | $100,000 to $250,000 | 0.01 | Harter, John | |
| St. Tammany | Dec 2008 | 058-01-0026 | LA 41 | La 41 In Pearl River | 3-lane La 41 In Pearl River | $1,000,000 to $2,500,000 | 0.01 | Schilling, Allison | Aug 2008 |
| Plaquemines | Mar 2009 | 062-02-0120 | LA 23 | Belle Chasse Tunnel | Electrical and Mechanical Repairs | $1,000,000 to $2,500,000 | 0.01 | Reed, Kevin | |
| Jefferson | Feb 2009 | 063-04-0034 | LA 18 | La 18(Us 90-w.Of Avondale Shipyard) | Widen to 4-lane | $2,500,000 to $5,000,000 | 1.45 | Riggs, Laura | Nov 2007 |
| Ascension | Jan 2009 | 063-10-0022 | LA 18 | Donaldsonville Sidewalk Rehab | Enhancement | $250,000 to $500,000 | 0.17 | Horton, Valerie | |
| Jefferson | Apr 2009 | 064-01-0040 | LA 1 | Caminada Bay Bridge | Bridge Replacement | $30,000,000 to $50,000,000 | 0.90 | Delatte, Brian | Jan 2009 |
| Terrebonne | Feb 2009 | 065-91-0033 | LA 24 | Presque Isle Bridge Repairs | Movable Bridge Mechanical Repairs | $250,000 to $500,000 | 0.01 | Berner, Darrick | |
| Jackson | Dec 2008 | 067-06-0036 | LA 4 | Caney Lake Bridge - La 34 | Stabilize Base and Overlay | $7,500,000 to $10,000,000 | 8.35 | Colquette, Paul | |
| Jackson | Mar 2009 | 068-03-0020 | LA 4 | La 499 - Caldwell Ph Line | Asphalt Surface Treatment | $250,000 to $500,000 | 5.31 | Colquette, Paul | |
| Union | Mar 2009 | 070-05-0019 | LA 2 | La 33 - La 143 | Asphalt Surface Treatment | $500,000 to $1,000,000 | 10.71 | Colquette, Paul | |
| Claiborne | Jan 2009 | 072-02-0012 | LA 9 | Lm 5.58 - US 71 | Chip Seal | $100,000 to $250,000 | 4.91 | Broadbent, Ronald | |
| Webster | Apr 2009 | 084-04-0006 | LA 615 | La 159 - Claiborne Ph Line | Cement Treat Base and Overlay | $1,000,000 to $2,500,000 | 4.36 | Baugh, Sam | |
| Bienville | Nov 2008 | 088-05-0019 | LA 154 | W.Jct US 80 - Kcs Railroad | Minor Overlay | $0 to $100,000 | 0.10 | Broadbent, Ronald | |
| Bienville | Dec 2008 | 089-04-0018 | LA 9 | La 517 - La 147 | Ac Widening (26'),2"ac Overlay | $2,500,000 to $5,000,000 | 7.90 | Baugh, Sam | |
| Caldwell | Dec 2008 | 091-09-0023 | LA 126 | La 845 - La 126 | Widen and Overlay | $500,000 to $1,000,000 | 1.03 | Mason, Ken | |
| Caddo | Feb 2009 | 102-01-0034 | LA 511 | La 526 - Pines Rd | Capacity and Safety Improvements | $15,000,000 to $20,000,000 | 2.10 | Toney, Patrick | Nov 2007 |
| Caddo | Feb 2009 | 102-02-0041 | LA 511 | La 511 E.B.@ I-20 Service Road | Lengthen Right Turn Lane | $100,000 to $250,000 | 0.06 | Drake, Bill | |
| Bossier | Apr 2009 | 102-03-0013 | LA 511 | Jimmy Davis E.B. Off Ramp | New Conc Pavement | $1,000,000 to $2,500,000 | 0.12 | Baugh, Sam | |
| Webster | Feb 2009 | 111-02-0020 | LA 531 | La 531 Turn Ln to I-20 Service Rd. | Left Turn Lane | $100,000 to $250,000 | 0.16 | Drake, Bill | |
| Sabine | Mar 2009 | 117-02-0012 | LA 118 | Kib Creek Bridge | New Bridge | $1,000,000 to $2,500,000 | 0.50 | Hicks, Melvin | Nov 2008 |
| Winn | Apr 2009 | 124-01-0015 | LA 34 | Cslm 6.90 - Jct. La 126 | Asph Widen and Overlay | $2,500,000 to $5,000,000 | 2.55 | Waguespack, Brent | Dec 2008 |
| Rapides | Feb 2009 | 149-01-0012 | LA 623 | La 623 (La 3225 - Wall Lane) | Rr Overpass | $10,000,000 to $15,000,000 | 1.50 | Waguespack, Brent | Jun 2007 |
| LaSalle | Feb 2009 | 149-04-0017 | LA 127 | .59 Mi.N.Little River-.5 Mi.S.La777 | Chip Seal Single | $250,000 to $500,000 | 8.20 | Broadbent, Ronald | |
| LaSalle | Dec 2008 | 152-02-0010 | LA 8 | Us 84 - Manifest | Overlay | $1,000,000 to $2,500,000 | 7.74 | Mason, Ken | |
| Union | Mar 2009 | 154-02-0015 | LA 15 | 1.4 Mi N Of La 549-3.8 Mi S La 550 | Asphalt Surface Treatment | $250,000 to $500,000 | 3.95 | Colquette, Paul | |
| Union | Dec 2008 | 154-03-0021 | LA 15 | La 15 Drainage | Drainage | $250,000 to $500,000 | 0.01 | Nilforoushan, Mehdi | May 2008 |
| Lincoln | Mar 2009 | 157-03-0020 | LA 145 | La 820 - Union Ph Line | Asphalt Surface Treatment | $500,000 to $1,000,000 | 8.17 | Colquette, Paul | |
| Union | Mar 2009 | 157-04-0009 | LA 145 | Lincoln Ph Line - La 15 | Asphalt Surface Treatment | $100,000 to $250,000 | 3.68 | Colquette, Paul | |
| East Carroll | Mar 2009 | 164-04-0015 | LA 577 | Madison Ph. Line - La 580 | Chip-seal Double | $250,000 to $500,000 | 6.94 | Broadbent, Ronald | |
| Concordia | Jan 2009 | 177-30-0021 | LA 131 | La 131 Relocation -1 Mi N. La 15 | Route Relocation (Levee Work) | $1,000,000 to $2,500,000 | 1.06 | Rabalais, Nick | |
| Calcasieu | Feb 2009 | 195-03-0029 | LA 385 | Common St (Tank Farm Rd - Petro Pt) | 5 Laning (Contingent On Bond Funds) | $20,000,000 to $30,000,000 | 3.38 | Porta, Buddy | Nov 2007 |
| Calcasieu | Apr 2009 | 196-01-0022 | LA 14 | La 14 Drainage | Drainage | $0 to $100,000 | 0.01 | Nilforoushan, Mehdi | |
| Allen | Dec 2008 | 197-04-0016 | LA 383 | 4 Miles W.Of US 165 - US 165 | Patch and Overlay | $1,000,000 to $2,500,000 | 3.98 | Landry, Pat | |
| St. Landry | Dec 2008 | 208-02-0014 | LA 357 | 3.59 Mi South Of US 190 - US 190 | Stabilize Base and Overlay | $1,000,000 to $2,500,000 | 3.59 | Draughon, Steve | |
| Acadia | Dec 2008 | 210-01-0011 | LA 91 | N.Jct La 98 - S.Jct La 98 | Stabilize Base and Overlay | $1,000,000 to $2,500,000 | 1.33 | Draughon, Steve | |
| Acadia | Dec 2008 | 211-02-0008 | LA 91 | Egan Jct. Local Rd. - La 98 | Base Replacement and Overlay | $2,500,000 to $5,000,000 | 5.98 | Draughon, Steve | |
| Lafayette | Jan 2009 | 213-05-0037 | LA 92 | Milton Bridge Trunnion Repairs | Trunnion Repairs | $1,000,000 to $2,500,000 | 0.01 | Berner, Darrick | |
| Iberville | Dec 2008 | 230-02-0018 | LA 75 | La 3066 - Bayou Sorrel Bridge | Single Lift Overlay | $1,000,000 to $2,500,000 | 5.86 | Beauvais, Hewitt | |
| Assumption | Dec 2008 | 232-01-0064 | LA 70 | Pierre Part Bridge Repairs | Movable Br. Grid Deck Replacement | $250,000 to $500,000 | 0.01 | Harter, John | |
| Iberia | Mar 2009 | 237-01-0028 | LA 86 | New Iberia Duperior Bridge Repairs | Movable Bridge Span Lock Repairs | $0 to $100,000 | 0.01 | Berner, Darrick | |
| Iberia | Feb 2009 | 240-03-0027 | LA 83 | Weeks Island Bridges | Bridge Replacement | $15,000,000 to $20,000,000 | 1.98 | Nakhleh, Jenan | Oct 2007 |
| Livingston | Dec 2008 | 260-07-0024 | LA 43 | La 442 - Parish Line | Cold Plane, Patch and Overlay | $2,500,000 to $5,000,000 | 5.80 | Schilling, Allison | |
| St. Helena | Dec 2008 | 260-08-0006 | LA 43 | Livingston Ph. Line - E.Jct La 16 | Cold Plane, Patch and Overlay | $1,000,000 to $2,500,000 | 3.07 | Schilling, Allison | |
| Livingston | Feb 2009 | 268-02-0018 | LA 447 | Us 190 - La 1019 | C.P, Patch and Overlay | $2,500,000 to $5,000,000 | 6.89 | Mcclendon, Jesse | |
| Livingston | Apr 2009 | 270-02-0018 | LA 441 | Tickfaw River Bridge Near Starnes | Bridge Replacement | $1,000,000 to $2,500,000 | 0.40 | Yap, Kian | Nov 2008 |
| Webster | Dec 2008 | 287-04-0002 | LA 793 | Black Lake Bayou - La 154 | Stabilize Base and Overlay | $0 to $100,000 | 0.41 | Baugh, Sam | |
| Bienville | Dec 2008 | 287-05-0011 | LA 793 | Black Lake Bayou - La 154 | Stabilize Base and Overlay | $500,000 to $1,000,000 | 4.84 | Baugh, Sam | |
| DeSoto | Nov 2008 | 298-03-0001 | LA3015 | Us 171 - La 175 | Overlay and Widen In Curves | $1,000,000 to $2,500,000 | 6.85 | Baugh, Sam | |
| Lincoln | Dec 2008 | 308-07-0011 | LA 545 | La 151 - La 146 | Stabilize Base and Overlay | $1,000,000 to $2,500,000 | 1.79 | Colquette, Paul | |
| Jackson | Apr 2009 | 316-02-0010 | LA 148 | La 146 - US 167 | Chip Seal 2 | $500,000 to $1,000,000 | 7.18 | Colquette, Paul | |
| Jackson | Apr 2009 | 316-03-0009 | LA 818 | Us 167 - Lincoln Ph Line | Chip Seal 2 | $100,000 to $250,000 | 1.85 | Colquette, Paul | |
| Jackson | Dec 2008 | 321-04-0013 | LA 505 | La 147 - La 4 | Stabilize Base and Overlay | $2,500,000 to $5,000,000 | 3.10 | Colquette, Paul | |
| East Carroll | Mar 2009 | 337-04-0011 | LA 877 | West Carroll Ph. Line - La 577 | Chip-seal Double | $0 to $100,000 | 0.61 | Broadbent, Ronald | |
| Catahoula | Dec 2008 | 354-01-0007 | LA 922 | Usace Park - 1.75 Mi Se. Of La 8 | Stabilize Base and Overlay | $1,000,000 to $2,500,000 | 2.03 | Mason, Ken | |
| Natchitoches | Feb 2009 | 360-05-0005 | LA 494 | La 484 - La 119 | Ctb and Overlay | $500,000 to $1,000,000 | 1.72 | Choate, Rodney | |
| Rapides | Feb 2009 | 369-02-0016 | LA1203 | La 1203 Roadway Flooding Project | Enlarge Cross Drain & Raise Roadway | $250,000 to $500,000 | 0.01 | Nilforoushan, Mehdi | Mar 2008 |
| Vernon | Mar 2009 | 373-01-0017 | LA 184 | La 184 Creek Bridge | Bridge Replacement | $1,000,000 to $2,500,000 | 0.40 | Kemp, Kelly | Oct 2008 |
| Beauregard | Jan 2009 | 377-01-0007 | LA 109 | Local Road - La 389 West | Chip Seal Single | $250,000 to $500,000 | 9.05 | Broadbent, Ronald | |
| Lafayette | Feb 2009 | 391-02-0009 | LA 98 | La 98 (500' East & West Of La 182) | Traffic Flow Improvements | $500,000 to $1,000,000 | 0.18 | Drake, Bill | |
| Vermilion | Dec 2008 | 393-01-0006 | LA 343 | La 14 - La 699 | Stabilize Base and Overlay | $2,500,000 to $5,000,000 | 6.13 | Draughon, Steve | |
| Iberia | Feb 2009 | 399-02-0015 | LA 671 | Us 90 - La 182 | Base Replacement | $7,500,000 to $10,000,000 | 1.80 | Babin, Teddy | |
| Lafourche | Nov 2008 | 407-01-0046 | LA 308 | Galliano Bridge Gearbox Repairs | Repairs to Gearboxes and Driveline | $100,000 to $250,000 | 0.01 | Harter, John | |
| Lafourche | Apr 2009 | 407-05-0018 | LA 308 | La 308 Shoulders(La 20-la 308&3185) | La 308 Shoulder Widening & Drainage | $500,000 to $1,000,000 | 1.17 | Branton, Jennifer | |
| Terrebonne | Apr 2009 | 412-04-0013 | LA 316 | La 316 | La 316 Shoulder Widening & Drainage | $500,000 to $1,000,000 | 1.46 | Branton, Jennifer | |
| Vernon | Jan 2009 | 417-01-0016 | LA 28 | Jct La 465 - Rapides Line | Widen to 4 Lanes | $20,000,000 to $30,000,000 | 4.30 | Moore, Darrell | Mar 2008 |
| Rapides | Mar 2009 | 417-02-0024 | LA 28 | Vernon Line - Jct La 121 | Widen to 4 Lanes | $30,000,000 to $50,000,000 | 8.90 | Moore, Darrell | Dec 2008 |
| Iberia | Feb 2009 | 424-04-0058 | US 90 | Us 90 @ La 675 Signing | Signing Improvements | $250,000 to $500,000 | 2.47 | Colvin, Jody | |
| Caddo | Apr 2009 | 427-01-0038 | LA3132 | La 3132(I-20 - .47 Mi. W Of La 526) | Pvt.Marking Replacement E & W Bnd ) | $250,000 to $500,000 | 0.01 | Allain, Peter | |
| Jefferson Davis | Jan 2009 | 450-03-0075 | I 10 | I-10:jeff Davis Parish Fence Repair | I-10 & I-210 Fence Repair (Rita) | $500,000 to $1,000,000 | 0.01 | Drake, Bill | |
| Jefferson Davis | Mar 2009 | 450-03-0076 | I 10 | I-10 (Calcasieu P/L - Acadia P/L) | Pvt.Marking Replacement | $100,000 to $250,000 | 0.01 | Allain, Peter | |
| Acadia | Apr 2009 | 450-04-0093 | I 10 | Interch Lighting I-10 @ La 95 Duson | Roadway Lighting | $500,000 to $1,000,000 | 0.53 | Douglas, Joseph | |
| Acadia | Jan 2009 | 450-04-0097 | I 10 | I-10(W.End Nezpique Br-lafayette Pl | Pvt. Marking Replacement(E & W Bnd) | $100,000 to $250,000 | 0.01 | Allain, Peter | |
| St. Martin | Feb 2009 | 450-06-0063 | I 10 | I-10 Pavement Marking Replacement | Striping/Pavement Marking Replace | $500,000 to $1,000,000 | 0.01 | Allain, Peter | |
| West Baton Rouge | Feb 2009 | 450-08-0051 | I 10 | La 1 In Port Allen to I-110 | Interstate Signing | $2,500,000 to $5,000,000 | 0.01 | Colvin, Jody | |
| East Baton Rouge | Feb 2009 | 450-09-0026 | I 10 | I-10 Mississippi River Bridge @ B.R | Bridge Rehab | $5,000,000 to $7,500,000 | 0.86 | Mumphrey, Ray | |
| St. Tammany | Feb 2009 | 450-18-0112 | I 10 | Acrow Disassembly, Relocate & Store | Acrow Disassembly, Relocate & Store | $2,500,000 to $5,000,000 | 0.01 | D'andrea, Artur | |
| Calcasieu | Jan 2009 | 450-30-0072 | I 210 | I 210 Glare Screen Replacement;rita | Glare Screen Replacement | $0 to $100,000 | 0.01 | Drake, Bill | |
| Calcasieu | Apr 2009 | 450-30-0076 | I 210 | I-210 Prien Lake Pier | Prien Lake Pier Protection Rehab | $20,000,000 to $30,000,000 | 0.01 | Fossier, Paul | |
| Calcasieu | Feb 2009 | 450-30-0077 | I 210 | I-210 Over City Streets | Joint Seal Replacement | $500,000 to $1,000,000 | 0.01 | Landry, Pat | |
| St. Charles | Feb 2009 | 450-37-0022 | I 310 | Mississippi River Br. (Luling) | Replace Cable Stays (Main Span) | $20,000,000 to $30,000,000 | 0.52 | Fossier, Paul | |
| Orleans | Apr 2009 | 450-90-0216 | I 10 | I-10 @ Metairie Rd. Interchange | Turnaround Improvements | $100,000 to $250,000 | 0.01 | Drake, Bill | |
| Orleans | Jan 2009 | 450-90-0219 | I 10 | I-10 @ Tulane&st.Bernard City St. | City St.Slide Plate Jt.Replacement | $250,000 to $500,000 | 0.01 | Monzon, John | |
| Caddo | Jan 2009 | 451-01-0127 | I 20 | I-20(Texas St Line-.37 Mi E La 3132 | Pvt. Marking Replacement(E & W Bnd) | $250,000 to $500,000 | 0.01 | Allain, Peter | |
| Bossier | Jan 2009 | 451-02-0051 | I 20 | Industrial - Fifi Bayou Bridge | Rehab | $7,500,000 to $10,000,000 | 3.70 | Thomas, Ben | |
| Webster | Feb 2009 | 451-03-0065 | I 20 | I-20(.34mi E US 80-.2mi West Of Pr) | Pvt.Marking Replacement (E & W Bnd) | $100,000 to $250,000 | 0.01 | Allain, Peter | |
| Webster | Dec 2008 | 451-03-0066 | I 20 | I-20 Over Dorcheat B. & Crows Creek | Joint Replacement | $100,000 to $250,000 | 0.01 | Maddox, Don | |
| Lincoln | Mar 2009 | 451-05-0117 | I 20 | I-20(2.45 Mi E La 563-ouachita P/L) | Pvt.Marking Peplacement E & W Bnd. | $100,000 to $250,000 | 0.01 | Allain, Peter | |
| Ouachita | Apr 2009 | 451-06-0150 | I 20 | I-20 (Lincoln Ph.Ln-.50mi E Garrett | Pvt.Marking Replacement(E & W Bnd.) | $250,000 to $500,000 | 0.01 | Allain, Peter | |
| Richland | Mar 2009 | 451-07-0071 | I 20 | I-20(1.18 Mi E Of P.Rd-madison P/L) | Pavement Marking Replacement | $0 to $100,000 | 0.01 | Allain, Peter | |
| Madison | Jan 2009 | 451-08-0074 | I 20 | I-20 (Us 65 - W.End Miss. River.Br) | Pvt.Marking Replacement(E&w Bnd Ln) | $100,000 to $250,000 | 0.01 | Allain, Peter | |
| Livingston | Dec 2008 | 454-02-0025 | I 12 | O'neal Lane - Pete's Hwy Overpass | Pvt Repl & Widening(Stage 0 Study) | $70,000,000 to $100,000,000 | 3.10 | Burst, Jeffery | |
| St. Tammany | Feb 2009 | 454-04-0076 | I 12 | Tangipahoa Ph.Line-us 190(Covington | Cold Plane, Drainage and Overlay | $15,000,000 to $20,000,000 | 10.13 | Thomas, Ben | |
| St. Landry | Apr 2009 | 455-02-0071 | I 49 | I-49 Pavement Marking Replacement | Striping/Pavement Marking Replace | $100,000 to $250,000 | 0.01 | Allain, Peter | |
| Avoyelles | Mar 2009 | 455-04-0021 | I 49 | I-49 Pavement Marking Replacement | Striping/Pavement Marking Replace | $250,000 to $500,000 | 0.01 | Allain, Peter | |
| Natchitoches | Feb 2009 | 455-06-0055 | I 49 | I-49 (Gumroot Br.-eight Mile Loop) | Embankment Repair | $100,000 to $250,000 | 0.23 | Hicks, Melvin | |
| Caddo | Feb 2009 | 455-09-0024 | I 49 | I-49 N(Mira Myrtis Rd.-la 168)seg B | Paving and Bridges | $20,000,000 to $30,000,000 | 4.66 | Umeozulu, Joe | |
| Statewide | Jan 2009 | 650-07-0015 | M/V Acadia | Vessel Re-powering | $500,000 to $1,000,000 | 0.00 | Reed, Kevin | ||
| Statewide | Jan 2009 | 650-14-0005 | M/V Iberville Ferry Hull Exam | U.S.C.G.5 Year Hull Exam & Repairs | $500,000 to $1,000,000 | 0.00 | Reed, Kevin | ||
| Statewide | Apr 2009 | 650-61-0004 | M/V Ross A.Grand Dry-docking Repair | Steel,Painting & Electrical Repair | $100,000 to $250,000 | 0.00 | Reed, Kevin | ||
| Statewide | Dec 2008 | 650-99-0021 | Landing Barge 304-003 Dry-dock | Steel,Painting & Electrical Repairs | $100,000 to $250,000 | 0.00 | Reed, Kevin | ||
| Statewide | Dec 2008 | 650-99-0022 | Landing Barge 304-004 Dry-dock | Steel,Painting & Electrical Repairs | $100,000 to $250,000 | 0.00 | Reed, Kevin | ||
| Statewide | Mar 2009 | 650-99-0023 | Landing Barge 305-068 Dry-docking | Steel,Painting & Electrical Repairs | $100,000 to $250,000 | 0.00 | Reed, Kevin | ||
| St. Martin | Jan 2009 | 693-09-0009 | I 10 | Breaux Bridge Wb & Eb Weigh Station | Emergency Operation Equipment | $0 to $100,000 | 0.01 | Silvio, Denny | |
| Jefferson | Dec 2008 | 704-26-0011 | Live Oak Blvd (Us 90 - Willswood) | Rehab (Phase 1 Srp) | $500,000 to $1,000,000 | 0.00 | Burst, Jeffery | ||
| Jefferson | Dec 2008 | 704-26-0013 | Lake Ave(Old Hammond H-w.Esplanade) | Rehab (Phase 1 Srp) | $500,000 to $1,000,000 | 0.00 | Burst, Jeffery | ||
| Jefferson | Dec 2008 | 704-26-0015 | Old Hammond Hwy.(17th St Can.-carr. | Rehab (Srp) | $500,000 to $1,000,000 | 0.00 | Burst, Jeffery | ||
| Orleans | Jan 2009 | 704-36-0027 | Pontchartrain(Robert E.Lee-vetrans) | Rehab (Phase 1 Srp) | $500,000 to $1,000,000 | 0.00 | Burst, Jeffery | ||
| Orleans | Jan 2009 | 704-36-0028 | Harrison Ave (West End - Orleans C) | Rehab (Phase 1 Srp) | $500,000 to $1,000,000 | 0.00 | Burst, Jeffery | ||
| Orleans | Jan 2009 | 704-36-0029 | Harrison Ave (Marconi - Wisner) | Rehab (Phase 1 Srp) | $500,000 to $1,000,000 | 0.00 | Burst, Jeffery | ||
| Orleans | Jan 2009 | 704-36-0030 | Canal Blvd.(Harrison-robert E.Lee) | Rehab (Phase 1 Srp) | $500,000 to $1,000,000 | 0.00 | Burst, Jeffery | ||
| Orleans | Apr 2009 | 704-36-0032 | Leon C.Simon(London C-elysian Field | Rehab (Phase 1 Srp) | $500,000 to $1,000,000 | 0.00 | Burst, Jeffery | ||
| Orleans | Apr 2009 | 704-36-0034 | Mirabeau(St.Bernard-elysian Fields) | Rehab (Phase 1 Srp) | $500,000 to $1,000,000 | 0.00 | Burst, Jeffery | ||
| Orleans | Apr 2009 | 704-36-0035 | Filmore (St.Bernard-elysian Fields) | Rehab (Phase 1 Srp) | $500,000 to $1,000,000 | 0.00 | Burst, Jeffery | ||
| Orleans | Apr 2009 | 704-36-0036 | St.Bernard Ave.(I-610 - Filmore) | Rehab (Phase 1 Srp) | $500,000 to $1,000,000 | 0.00 | Burst, Jeffery | ||
| Orleans | Apr 2009 | 704-36-0037 | Paris Ave. (I-610 - Mirabeau) | Rehab (Phase 1 Srp) | $500,000 to $1,000,000 | 0.00 | Burst, Jeffery | ||
| Orleans | Apr 2009 | 704-36-0038 | Elysian Fields Ave(Lakeshore-us 90) | Rehab (Phase 1 Srp) | $500,000 to $1,000,000 | 0.00 | Burst, Jeffery | ||
| Orleans | Apr 2009 | 704-36-0039 | Franklin Ave (I-610 - La 46) | Rehab (Phase 1 Srp) | $500,000 to $1,000,000 | 0.00 | Burst, Jeffery | ||
| Orleans | Mar 2009 | 704-36-0040 | Carrollton Ave. (I-10 - Claiborne) | Rehab (Phase 1 Srp) | $500,000 to $1,000,000 | 0.00 | Burst, Jeffery | ||
| Orleans | Mar 2009 | 704-36-0041 | Carrollton Ave(Claiborne-st.Charles | Rehab (Phase 1 Srp) | $500,000 to $1,000,000 | 0.00 | Burst, Jeffery | ||
| Orleans | Apr 2009 | 704-36-0045 | Magazine St.(Us 90.B.-.Nashville) | Rehab (Phase 1 Srp) | $500,000 to $1,000,000 | 0.00 | Burst, Jeffery | ||
| Orleans | Feb 2009 | 704-36-0046 | Louisiana (St.Charles - Magazine) | Rehab (Phase 1 Srp) | $500,000 to $1,000,000 | 0.00 | Burst, Jeffery | ||
| Orleans | Apr 2009 | 704-36-0047 | Nashville(Claiborne-tchoupitoulas) | Rehab (Phase 1 Srp) | $500,000 to $1,000,000 | 0.00 | Burst, Jeffery | ||
| Orleans | Apr 2009 | 704-36-0048 | Claiborne (Us 90 - St.Charles) | Rehab (Phase 1 Srp) | $500,000 to $1,000,000 | 0.00 | Burst, Jeffery | ||
| Orleans | Mar 2009 | 704-36-0049 | St.Charles (Nashville-s.Carrollton) | Rehab (Phase 1 Srp) | $500,000 to $1,000,000 | 0.00 | Burst, Jeffery | ||
| Orleans | Apr 2009 | 704-36-0062 | Dowmnman Rd. (Hayne Blvd - US 90) | Rehab (Phase 1 Srp) | $500,000 to $1,000,000 | 0.00 | Burst, Jeffery | ||
| Orleans | Mar 2009 | 704-36-0068 | Poydras (Claiborne - Broad) | Rehab (Phase 1 Srp) | $500,000 to $1,000,000 | 0.00 | Burst, Jeffery | ||
| Orleans | Mar 2009 | 704-36-0069 | Mlk Blvd.(Claiborne - Broad) | Rehab (Phase 1 Srp) | $500,000 to $1,000,000 | 0.00 | Burst, Jeffery | ||
| Orleans | Apr 2009 | 704-36-0070 | Almonaster Rd.(Jourdan - Read) | Rehab (Phase 1 Srp) | $500,000 to $1,000,000 | 0.00 | Burst, Jeffery | ||
| Orleans | Apr 2009 | 704-36-0075 | Alvar & Poland(St.Claude-florida A) | Rehab (Phase 1 Srp) | $500,000 to $1,000,000 | 0.00 | Burst, Jeffery | ||
| Orleans | Mar 2009 | 704-36-0077 | Washington (S.Broad-s.Carrollton) | Rehab (Phase 1 Srp) | $500,000 to $1,000,000 | 0.00 | Burst, Jeffery | ||
| Orleans | Jan 2009 | 704-36-0078 | Vetrans(Pontchartrain-17th St Canal | Rehab (Phase 1 Srp) | $70,000,000 to $100,000,000 | 0.00 | Burst, Jeffery | ||
| Orleans | Apr 2009 | 704-36-0085 | Jefferson (St.Charles-tchoupitoulas | Rehab (Phase I Srp) | $500,000 to $1,000,000 | 0.00 | Burst, Jeffery | ||
| St. Bernard | Feb 2009 | 704-44-0012 | Jean Lafitte(La 46-florida Walk Ca) | Rehab (Phase 1 Srp) | $500,000 to $1,000,000 | 0.00 | Burst, Jeffery | ||
| St. Bernard | Feb 2009 | 704-44-0013 | Patricia St.(Jean Lafitte - Cougar) | Rehab (Phase 1 Srp) | $500,000 to $1,000,000 | 0.00 | Burst, Jeffery | ||
| Avoyelles | Dec 2008 | 713-05-0106 | Regard Road Bridge | Bridge Replacement | $500,000 to $1,000,000 | 0.00 | Pentek, Gary | ||
| Caddo | Feb 2009 | 713-09-0021 | White Springs Road Bridge | Bridge Replacement | $1,000,000 to $2,500,000 | 0.00 | Pentek, Gary | ||
| Claiborne | Jan 2009 | 713-14-0108 | Old Arcadia Road Bridges | Bridge Replacement | $1,000,000 to $2,500,000 | 0.02 | Pentek, Gary | ||
| East Baton Rouge | Nov 2008 | 713-17-0041 | Baker Road Bridge | Bridge Replacement | $250,000 to $500,000 | 0.00 | Pentek, Gary | ||
| East Feliciana | Dec 2008 | 713-19-0107 | Thompson Creek Rd. Bridge | Bridge Replacement | $1,000,000 to $2,500,000 | 0.00 | Pentek, Gary | ||
| Grant | Dec 2008 | 713-22-0107 | Moccasin Branch&frazier Cemetery Rd | Bridge Replacement | $500,000 to $1,000,000 | 0.02 | Pentek, Gary | ||
| Jefferson | Dec 2008 | 713-26-0105 | 26th @ Canal Number 17 | Bridge Replacement | $1,000,000 to $2,500,000 | 0.00 | Pentek, Gary | ||
| Orleans | Jan 2009 | 713-36-0100 | Park Island Bridge | Bridge Replacement | $1,000,000 to $2,500,000 | 0.00 | Pentek, Gary | ||
| Rapides | Dec 2008 | 713-40-0127 | Forestry Road Bridge | Bridge Replacement | $1,000,000 to $2,500,000 | 0.00 | Pentek, Gary | ||
| St. Tammany | Jan 2009 | 713-52-0100 | Carr Drive Bridge | Bridge Replacement | $1,000,000 to $2,500,000 | 0.00 | Pentek, Gary | ||
| Tensas | Feb 2009 | 713-54-0104 | Ice House Road | Bridge Replacement | $250,000 to $500,000 | 0.01 | Pentek, Gary | ||
| Vermilion | Dec 2008 | 713-57-0105 | Bridges In Vermilion Parish | Bridge Replacement | $1,000,000 to $2,500,000 | 0.00 | Pentek, Gary | ||
| Avoyelles | Feb 2009 | 714-05-0110 | Us 71 @ Ebony St.Intersection Imp | Intersection Improvemoments | $100,000 to $250,000 | 0.00 | Hicks, Melvin | ||
| Orleans | Nov 2008 | 737-36-0013 | New Orleans Rtmc Integration | New Equipment | $1,000,000 to $2,500,000 | 0.00 | Delaney, Elizabeth | ||
| District 62 | Apr 2009 | 737-90-0065 | Interstate Bridges Over Var.Xings | Bridge Deck Joint Seal Replacements | $1,000,000 to $2,500,000 | 0.00 | Schilling, Allison | ||
| Franklin | Feb 2009 | 737-91-0027 | Districtwide Intr. Rumble Strips | Rumble Strips | $100,000 to $250,000 | 0.00 | Mason, Ken | ||
| District 58 | Apr 2009 | 737-91-0029 | La Route Bridges Over Various Xings | Bridge Deck Joint Seal Replacements | $500,000 to $1,000,000 | 0.00 | Mason, Ken | ||
| District 04 | Mar 2009 | 737-94-0050 | I-49 & I-20(Caddo P/L-bossier P/L | Raised Pvt.Marking Replacement | $100,000 to $250,000 | 0.01 | Allain, Peter | ||
| Orleans | Mar 2009 | 737-95-0069 | Detail Striping and Channelizing | Striping and Channelizing Devices | $100,000 to $250,000 | 0.00 | Drake, Bill | ||
| Statewide | Dec 2008 | 737-99-0914 | Amber Alert Dms Retrofit | Dms Retrofit | $250,000 to $500,000 | 0.10 | Delaney, Elizabeth | ||
| Statewide | Feb 2009 | 737-99-0953 | Delta Parish Rural Intersection Imp | Delta Parishes Intersection Imp | $1,000,000 to $2,500,000 | 0.00 | Chapman, Jim | ||
| Rapides | Feb 2009 | 742-07-0098 | Susek Drive In Pineville (Np) | Reconstruction | $7,500,000 to $10,000,000 | 2.30 | Porta, Buddy | Oct 2006 | |
| Calcasieu | Feb 2009 | 742-10-0114 | Elliot Rd @ Gauthier | Add Turn Lanes and Signals | $1,000,000 to $2,500,000 | 0.00 | Waguespack, Brent | Dec 2008 | |
| East Baton Rouge | Feb 2009 | 742-17-0008 | Flannery @ Florida (Np) | Intersection Improvement | $2,500,000 to $5,000,000 | 0.15 | Riggs, Laura | Nov 2008 | |
| East Baton Rouge | Feb 2009 | 742-17-0135 | Millerville (I-12 - Hf Rd) (C&g) | Clearing For 5 Lanes | $250,000 to $500,000 | 0.39 | Riggs, Laura | Nov 2008 | |
| East Baton Rouge | Mar 2009 | 742-17-0143 | Centralthruway(Frenchtown-sullivan) | C & G and Embankment Construction | $2,500,000 to $5,000,000 | 1.20 | Riggs, Laura | May 2005 | |
| East Baton Rouge | Mar 2009 | 742-17-0146 | S. Sherwood Forest Blvd | Clearing and Grubbing | $250,000 to $500,000 | 0.00 | Riggs, Laura | Apr 2006 | |
| East Baton Rouge | Dec 2008 | 742-17-0147 | Central Thruway Bridges #2 Sul/Iccn | New Bridges | $10,000,000 to $15,000,000 | 1.20 | Riggs, Laura | ||
| Jefferson | Feb 2009 | 742-26-0056 | Lapalco (Brooklyn Ave - Murphy C.) | Overlay | $1,000,000 to $2,500,000 | 0.33 | Riggs, Laura | ||
| Jefferson | Feb 2009 | 742-26-0066 | Segnette Blvd.(Lapalco Blvd-us 90b) | Overlay | $2,500,000 to $5,000,000 | 0.00 | Riggs, Laura | Nov 2008 | |
| Orleans | Jan 2009 | 742-36-0110 | Robert E.Lee Blvd.(Paris - Pratt) | Reconstruct | $1,000,000 to $2,500,000 | 0.00 | Riggs, Laura | May 2005 | |
| Orleans | Jan 2009 | 742-36-0123 | Woodland Drive (Tullis - Degaulle) | Conc Pavement Rehabilitation | $5,000,000 to $7,500,000 | 0.00 | Riggs, Laura | ||
| Orleans | Dec 2008 | 742-36-0138 | Magazine(Calliope Str-st Joseph Str | Rehabilitation | $1,000,000 to $2,500,000 | 0.14 | Riggs, Laura | Oct 2008 | |
| Calcasieu | Feb 2009 | 744-10-0021 | Sidewalk On Prater Road | Sidewalk | $100,000 to $250,000 | 0.66 | Horton, Valerie | ||
| Franklin | Jan 2009 | 744-21-0008 | Havard Street Pedestrian Walkway | New Sidewalks/Bike Path | $100,000 to $250,000 | 0.00 | Horton, Valerie | ||
| District 04 | Dec 2008 | 745-94-0005 | LA 2 | 4 Interpretitive Kiosks Nw La | Construct 4 Interpretitive Kiosks | $100,000 to $250,000 | 0.01 | Horton, Valerie | |
| Bossier | Jan 2009 | 808-07-0051 | LA3105 | La 3105 @ US 80 | Right Turn Lane | $250,000 to $500,000 | 0.10 | Baugh, Sam | Oct 2007 |
| Calcasieu | Dec 2008 | 810-26-0019 | LA 379 | La 27 - La 378 | Patch and Overlay | $2,500,000 to $5,000,000 | 7.21 | Landry, Pat | |
| Caldwell | Dec 2008 | 811-03-0018 | LA 845 | La 547 - La 126 | Patch and Overlay | $500,000 to $1,000,000 | 1.95 | Mason, Ken | |
| Caldwell | Dec 2008 | 811-14-0002 | LA 547 | La 845 - La 844 | Patch and Overlay | $100,000 to $250,000 | 0.24 | Mason, Ken | |
| Catahoula | Feb 2009 | 813-07-0009 | LA 915 | La 916 - La 913 | Chip Seal Single | $0 to $100,000 | 0.82 | Broadbent, Ronald | |
| Concordia | Feb 2009 | 815-17-0006 | LA 565 | La 129 - La 15 | Chip Seal Single | $250,000 to $500,000 | 8.48 | Broadbent, Ronald | |
| East Baton Rouge | Mar 2009 | 817-41-0008 | LA3245 | O'neal Lane (I-12 - Florida Blvd) | Widening | $10,000,000 to $15,000,000 | 1.82 | Borne, Fred | Dec 2008 |
| East Carroll | Mar 2009 | 818-08-0008 | LA 881 | La 134 - La 581 | Chip-seal Double | $100,000 to $250,000 | 3.51 | Broadbent, Ronald | |
| Evangeline | Feb 2009 | 820-03-0011 | LA 748 | La 1169 - St. Landry Ph. Line | Stabilize Base and Overlay | $1,000,000 to $2,500,000 | 2.43 | Draughon, Steve | |
| Grant | Jan 2009 | 822-05-0006 | LA1241 | La 1241 Left Turn Lns. @ Grant Ele. | Left Turn Lanes | $1,000,000 to $2,500,000 | 0.01 | Richard, Ryan | Oct 2008 |
| Jackson | Apr 2009 | 825-09-0012 | LA 811 | La 542 - US 167 | Chip Seal 2 | $100,000 to $250,000 | 2.99 | Colquette, Paul | |
| Jefferson | Feb 2009 | 826-06-0020 | LA 301 | La 301 (Bayou Villars - La 45) | C.P. and Overlay | $1,000,000 to $2,500,000 | 3.00 | Branton, Jennifer | |
| Jefferson | Mar 2009 | 826-10-0008 | LA 5604 | La 560-4 (La 45 - Bayou Barataria) | C.P. and Overlay | $250,000 to $500,000 | 0.89 | Branton, Jennifer | |
| Lincoln | Mar 2009 | 831-07-0036 | LA 150 | La 149 - Ruston | Asphalt Surface Treatment | $100,000 to $250,000 | 3.33 | Colquette, Paul | |
| Livingston | Apr 2009 | 832-35-0001 | LA1020 | La 1019 - End Of Control @ Amite R. | Minor Overlav | $250,000 to $500,000 | 1.87 | Broadbent, Ronald | |
| Plaquemines | Dec 2008 | 838-03-0023 | LA 406 | Woodland Hwy.(La 23-planters Canal) | Widen and Overlay | $1,000,000 to $2,500,000 | 1.63 | Branton, Jennifer | |
| Rapides | Mar 2009 | 840-22-0024 | LA 498 | La 498 (End Of PCCP - England Dr.) | Minor Overlay | $100,000 to $250,000 | 0.65 | Broadbent, Ronald | |
| St. Charles | Dec 2008 | 845-17-0014 | LA 50 | La 50 (La 48 - US 61) | Overlay and Drainage Improvements | $1,000,000 to $2,500,000 | 0.84 | Branton, Jennifer | |
| St. Helena | Apr 2009 | 846-11-0007 | LA1044 | La 432 - Mississippi State Line | Chip Seal-single | $100,000 to $250,000 | 5.73 | Broadbent, Ronald | |
| St. John Baptist | Apr 2009 | 848-06-0003 | LA 639 | La 18 - Tp RR | Minor Overlay | $0 to $100,000 | 0.40 | Broadbent, Ronald | |
| St. John Baptist | Dec 2008 | 848-17-0004 | LA3217 | La 628 - US 61 | Cold Plane, Patch and Overlay | $250,000 to $500,000 | 1.31 | Schilling, Allison | |
| St. John Baptist | Dec 2008 | 848-18-0007 | LA3223 | La 44 - US 61 | Cold Plane, Patch and Overlay | $100,000 to $250,000 | 0.37 | Schilling, Allison | |
| St. John Baptist | Dec 2008 | 848-19-0006 | LA3224 | La 44 - US 61 | Cold Plane, Patch and Overlay | $0 to $100,000 | 0.23 | Schilling, Allison | |
| St. Tammany | Mar 2009 | 852-06-0008 | LA1077 | La 1077 - La 25 | Aphalt Overlay | $2,500,000 to $5,000,000 | 6.20 | Schilling, Allison | |
| Tangipahoa | Mar 2009 | 853-10-0016 | LA1040 | La 1040 (Hammond) | Realinment In City Of Hammond | $1,000,000 to $2,500,000 | 1.13 | Schilling, Allison | Apr 2008 |
| Tangipahoa | Jan 2009 | 853-18-0006 | LA1054 | La 10 - La 1058 | C.P.,Base,& Overlay | $1,000,000 to $2,500,000 | 4.04 | Mcclendon, Jesse | |
| Tangipahoa | Dec 2008 | 853-39-0007 | LA3158 | I-12 - US 190 | A3 Asph Ovly Asp Pv | $500,000 to $1,000,000 | 1.94 | Schilling, Allison | |
| Tangipahoa | Dec 2008 | 853-39-0008 | LA3158 | Intersection Improv. At Old Cov Hwy | Intersection Improvements | $250,000 to $500,000 | 0.11 | Drake, Bill | |
| Vermilion | Mar 2009 | 857-66-0010 | LA3147 | Freshwatew City - Humble Canal | 6" Limestone & 3 Course Ast | $1,000,000 to $2,500,000 | 3.13 | Babin, Teddy | |
| Washington | Apr 2009 | 859-09-0019 | LA 430 | La 1069 - La 438 | Chip Seal-single | $250,000 to $500,000 | 9.97 | Broadbent, Ronald | |
| Claiborne | Apr 2009 | 860-10-0002 | LA 615 | La 159 - Claiborne Ph Line | Ac Widen and Overlay | $100,000 to $250,000 | 0.36 | Baugh, Sam |