Project Item Summary

Items for Project 278-01-0010

go back

Scheduled for Letting 01/25/06
 
Project List
JCT. LA. 22 - JCT. U.S. 190
Click Download Items button to save a comma delimited file of the Items for this Project.

NOTE: Items and quantities shown are provided for informational purposes only and are subject to revision.

Item Description Unit Quantity
202-02-H removal of guard rail LNFT 1,042
203-08 borrow (vehicular measurement) CUYD 1,200
401-02 aggregate surface course (adjusted vehicular measurement) CUYD 1,357
502-01 superpave asphaltic concrete TON 18,163.6
502-01-A superpave asphaltic concrete, drives, turnouts and miscellaneous TON 469.5
509-01 cold planing asphaltic pavement SQYD 78,355
509-02 contractor retained reclaimed asphaltic pavement CUYD - 1,645
701-02-D/E cross drain pipe arch (24" equiv. rcpa or 30" equiv. cmpa) LNFT 44
701-08 relaying pipe LNFT 16
701-10-M reinforced concrete pipe (extension)(36") LNFT 24
701-15 concrete collar EACH 5
704-01-B guard rail (single thrie beam)(6'-3" post spacing) LNFT 160.0
704-03 blocked out guard rail LNFT 331.3
704-07-A guard rail bridge attachments (single thrie beam) LNFT 75.0
704-08-B guard rail transitions (double thrie beam) LNFT 300.0
704-11-A guard rail end treatment (flared) EACH 12
707-04 asphaltic curb LNFT 120.0
713-01 temporary signs & barricades LUMP LUMP
713-03-C temporary pavement markings (8" width) LNFT 675
713-03-E temporary pavement markings (24" width) LNFT 888
713-04-A temporary pavement markings (broken line)(4" width)(4' length) MILE 12.600
713-04-B temporary pavement markings (broken line)(4" width)(10' length) MILE 9.900
713-05-A temporary pavement markings (solid line)(4" width) MILE 35.100
713-06-A temporary pavement legends and symbols (arrow) EACH 6
713-06-C temporary pavement legends and symbols (only) EACH 6
724-01-B pavement patching (12" minimum thickness) SQYD 2,712
724-02 pavement widening SQYD 425.0
726-01 bedding material CUYD 9.8
727-01 mobilization LUMP LUMP
729-16-C object marker assembly (type 3) EACH 12
731-02 reflectorized raised pavement markers EACH 675
732-01-C plastic pavement striping (8" width) LNFT 270
732-01-E plastic pavement striping (24" width) LNFT 355
732-02-A plastic pavement striping (solid line) (4" width) MILE 14.040
732-03-A plastic pavement striping (broken line)(4" width) MILE 3.960
732-04-A plastic pavement legends & symbols (arrow) EACH 2
732-04-C plastic pavement legends & symbols (only) EACH 2
735-01 mailboxes EACH 31
735-02 mailbox supports (single) EACH 31
736-09 loop detector LNFT 150
736-10 underground junction box EACH 1
736-11 conduit (1"pec) LNFT 25
739-01 hydro-seeding ACRE .50
740-01 construction layout LUMP LUMP
744-01 traffic control management LUMP LUMP
S-001 u-channel post installation EACH 70
S-002 cleaning existing ditches LNFT 200
S-003 dynamic message sign unit EACH 2
S-101 barrier rail rehabilition LNFT 606.0