ADHESIVE FOR RAISED PAVEMENT MARKERS
DOTD Designation: S 606-99
BITUMINOUS ADHESIVE
I. General
A. Equipment
1. DOTD stamp, ink pad and suitable markers for identification.
B. Safety Precautions
It is the responsibility of the user of this sampling method to establish appropriate safety practices including, but not limited to, lifting heavy containers.
II. Sampling at the Warehouse
A. Warehouse Responsibilities
1. Notify the District Laboratory in the District in which the storage facility is located for material approval allowing adequate time for scheduling by the District Laboratory.
B. District Laboratory Responsibilities
1. Upon arrival at the warehouse, identify the bituminous adhesive by DOTD lot. Each DOTD lot shall not contain more than one manufacturer's lot and shall not exceed 20,000 lb.
C. Certificate of Delivery From the Warehouse
Upon receiving approval and a passing laboratory number from the Materials & Testing Section, submit with each lot of bituminous adhesive a Certificate of Delivery to the Project Engineer along with a copy to the Materials & Testing Section. Each CD must be signed by an authorized representative of the company.
III. Sampling at the Project Site
Note 1: Use this procedure only for
those suppliers not having permanent storage facilities within the state. Sample for
acceptance at the project site on which the bituminous adhesive is to be used.
A. Contractor's Responsibilities
1. Provide adequate storage facilities at the project site for all bituminous adhesive for the purpose of obtaining acceptance of the adhesive prior to application.
B. Project Engineer Responsibilities
1. Identify the bituminous adhesive by manufacturer's lot in increments not to exceed 20,000 lb.
EPOXY ADHESIVE
I. General
A. Equipment
1. Sampling device - two small, clean scoops.
B. Safety Precautions
It is the responsibility of the user of this sampling method to establish appropriate safety practices including, but not limited to, exposure to hazardous fumes and lifting heavy containers.
II. Sampling at the Warehouse
A. Warehouse Responsibilities
1. Notify the District Laboratory in the District in which the storage facility is located for material approval allowing adequate time for scheduling by the District Laboratory.
B. District Laboratory Responsibilities
Note 2: Upon request from the Warehouse, obtain a random sample per DOTD lot of epoxy adhesive.
1. Upon arrival at the warehouse, identify the epoxy adhesive by DOTD lot. Each DOTD lot shall not exceed 50 gal of each component.
C. Certificate of Delivery From the Warehouse
Upon receiving approval and a passing laboratory number from the Materials & Testing Section, submit with each DOTD lot of epoxy adhesive a Certificate of Delivery to the Project Engineer along with a copy to the Materials & Testing Section. Each CD must be signed by an authorized representative of the company.
III. Sampling at the Project Site
Note 3: Use this procedure only for
those suppliers not having permanent storage facilities within the state. Sample for
acceptance at the project site on which the epoxy adhesive is to be used.
A. Contractor's Responsibilities
1. Provide adequate storage facilities at the project site for all epoxy adhesive for the purpose of obtaining acceptance of the adhesive prior to application.
B. Project Engineer Responsibilities
1. Identify the epoxy adhesive by manufacturer's lot in increments not to exceed 50 gal of each component.
Go to Form 03-22-0026,
Certificate of Delivery for Pavement Marking Materials (Excluding Paint)