SAMPLING FRESH CONCRETE

DOTD Designation: S 301-99

I. Sampling from Transports Without Discharge Chutes

Note 1: Be careful when sampling fresh concrete from a pile. Do not disturb the prepared subgrade.

II. Sampling from Transports or Mixers With Discharge Chutes

Note 2: The point of the batch at which the sample is to be obtained will be determined by the purpose of the test to be performed (control, acceptance or IA). Concrete for acceptance and IA tests will be sampled from midbatch. Concrete for control tests will be sampled as specifed, directed or required.

III. Sampling from Pumps