Projects Under Construction

District 04

    Updated 16 Mar 2010

Districtwide Projects

Bienville Parish

Note: The estimated completion date is based on the work order date and the contract days allowed.

Arcadia Sidewalk Program, Phase I
001-06-0052 - Sidewalks/bike paths
Proj. Engr: North, David     Route: US 80
Contractor: Rmd Holdings Ltd     Miles: 0.82
Work Order Date Contract Amount Estimated Completion Date
2008-10-24 $198,111 2009-05-04


LA 4 Bridges Near Friendship
067-04-0025 - New location/replacement of bridge
Proj. Engr: North, David     Route: LA 4
Contractor: James Construction Group LLC     Miles: 0.62
Work Order Date Contract Amount Estimated Completion Date
2009-02-02 $3,724,538 2010-05-20


Bossier Parish

Note: The estimated completion date is based on the work order date and the contract days allowed.

Eastwood to Webster Parish Line (Westbound Lanes)
001-03-0079 - Asphalt overlay of asphalt pavement
Proj. Engr: Christner, Steve     Route: US 79 US 80
Contractor: Best-Yet Builders, LLC     Miles: 7.20
Work Order Date Contract Amount Estimated Completion Date
2009-12-17 $2,460,967 2010-05-18


Benton Road RR Overpass
044-01-0038 - New location/replacement of bridge
Proj. Engr: Christner, Steve     Route: LA 3
Contractor: Austin Bridge     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2006-03-27 $11,562,512 2009-09-13


LA 157 Improvements
082-03-0027 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Christner, Steve     Route: LA 157
Contractor: F. J. Burnell, Inc.     Miles: 0.42
Work Order Date Contract Amount Estimated Completion Date
2009-08-05 $1,016,878 2010-01-04


Jimmy Davis Eastbound Off Ramp
102-03-0013 - Concrete new pavement
Proj. Engr: Christner, Steve     Route: LA 511
Contractor: F. J. Burnell, Inc.     Miles: 0.34
Work Order Date Contract Amount Estimated Completion Date
2010-01-21 $852,233 2010-04-23


Parks Road Bridge Over Cypress Bayou
713-08-0108 - New location/replacement of bridge
Proj. Engr: Christner, Steve     Route:
Contractor: James Construction Group LLC     Miles: 0.31
Work Order Date Contract Amount Estimated Completion Date
2008-10-30 $2,318,777 2010-02-27


Caddo Parish

Note: The estimated completion date is based on the work order date and the contract days allowed.

US 80 Add Center Turn Lanes
001-02-0035 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Hollier, Jim     Route: US 80
Contractor: F. J. Burnell, Inc.     Miles: 0.23
Work Order Date Contract Amount Estimated Completion Date
2009-09-22 $774,966 2010-03-21


West 70th Street (La 526 - Pines Road)
102-01-0034 - Concrete new pavement
Proj. Engr: Hollier, Jim     Route: LA 511
Contractor: F. J. Burnell, Inc.     Miles: 2.42
Work Order Date Contract Amount Estimated Completion Date
2009-08-26 $13,393,690 2011-03-21


Jct. Existing 5-Lane to Jct. La 1
103-01-0025 - Asphalt new pavement-new roadway/new alignments
Proj. Engr: Hollier, Jim     Route: LA 523
Contractor: Gilchrist Construction Co. LLC     Miles: 2.86
Work Order Date Contract Amount Estimated Completion Date
2008-07-27 $23,522,747 2010-07-11


Shreveport ITS Near Term Phase I
451-01-0113 - Signalization
Proj. Engr: Hollier, Jim     Route: I-20
Contractor: Wye Electric, Inc.     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2008-07-20 $1,946,401 2009-12-22


Monkhouse to US 79
451-01-0118 - Signing
Proj. Engr: Wall, Greg     Route: I-20
Contractor: Alpha Service and Products, Inc.     Miles: 3.22
Work Order Date Contract Amount Estimated Completion Date
2007-09-17 $442,921 2008-05-01


Mccain Creek Bridge Replacement
451-30-0026 - Bridges reconditioned
Proj. Engr: Murphy, Michael     Route: I-220
Contractor: Eutaw Construction Co. Inc.     Miles: 0.75
Work Order Date Contract Amount Estimated Completion Date
2009-01-26 $12,363,626 2010-06-06


I-49 North (La 173 - La 169)
455-09-0004 - Concrete new pavement
Proj. Engr: Christner, Steve     Route:
Contractor: T.J. Lambrecht Construction, I     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2010-01-29 $10,148,241 2011-09-30


I-49 North (Us 71 (South) to La 2)
455-09-0007-R1 - Concrete new pavement
Proj. Engr: Christner, Steve     Route: I-49
Contractor: T.J. Lambrecht Construction, I     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2009-11-16 $41,636,832 2011-10-31


I-49 North, (La 2 to Mira-Myrtis Road)
455-09-0008 - Concrete new pavement
Proj. Engr: Murphy, Michael     Route: I-49 US 71
Contractor: T.J. Lambrecht Construction, Inc.     Miles: 3.17
Work Order Date Contract Amount Estimated Completion Date
2008-08-11 $20,246,453 2010-01-28


I-49 North (La 168 to Arkansas State Line)
455-09-0023 - Concrete new pavement
Proj. Engr: Murphy, Michael     Route: I-49
Contractor: Denton-James LLC     Miles: 3.44
Work Order Date Contract Amount Estimated Completion Date
2009-02-12 $20,957,075 2010-04-02


I-49 North (Mira-Myrtis Road to La 168)
455-09-0024 - New location/replacement of bridge
Proj. Engr: Murphy, Michael     Route: I-49
Contractor: Austin Bridge & Road, Lp     Miles: 5.80
Work Order Date Contract Amount Estimated Completion Date
2009-05-18 $31,261,214 2010-10-04


Rest Area Improvements I-20 at Greenwood
694-01-0005 - Rest areas
Proj. Engr: Rodi, Ronald     Route: I-20
Contractor: F. J. Burnell, Inc.     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2008-04-28 $6,897,469 2009-07-31


Turn Lanes at Linwood Avenue
809-08-0048 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Hollier, Jim     Route: LA 526
Contractor: Blount Bros. Construction, Inc     Miles: 0.22
Work Order Date Contract Amount Estimated Completion Date
2009-08-04 $429,311 2009-11-04


Claiborne Parish

Note: The estimated completion date is based on the work order date and the contract days allowed.

L & Nw Railroad Overpass
085-08-0025 - New location/replacement of bridge
Proj. Engr: North, David     Route: LA 146
Contractor: Jb James Construction LLC     Miles: 0.20
Work Order Date Contract Amount Estimated Completion Date
2010-01-04 $1,859,692 2010-09-14


LA 146 Bridges Near Vienna and La 151 Creek Bridges
085-08-0027 - New location/replacement of bridge
Proj. Engr: Shapiro, Jeff     Route: LA 146
Contractor: James Construction Group LLC     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2009-08-10 $7,627,889 2013-01-02


Old Arcadia Road Bridges
713-14-0108 - New location/replacement of bridge
Proj. Engr: North, David     Route:
Contractor: Louisiana Bridge, Inc.     Miles: 0.23
Work Order Date Contract Amount Estimated Completion Date
2009-05-01 $1,105,319 2010-02-28


Homer By-Pass Embankment
814-07-0004 - Embankment
Proj. Engr: North, David     Route: LA 3244
Contractor: Eutaw Construction Co. Inc.     Miles: 3.83
Work Order Date Contract Amount Estimated Completion Date
2008-10-13 $6,490,314 2010-12-20


DeSoto Parish

Note: The estimated completion date is based on the work order date and the contract days allowed.

State Route In Mansfield
021-03-0031 - Concrete new pavement
Proj. Engr: Buskie, Stephen     Route: US 171 US 84
Contractor: Best-Yet Builders, LLC     Miles: 9.00
Work Order Date Contract Amount Estimated Completion Date
2008-04-11 $44,697,756 2010-03-24


Sabine Parish Line - South Mansfield
025-05-0023 - Asphalt widening and overlay
Proj. Engr: Buskie, Stephen     Route: US 171
Contractor: Austin Bridge & Road, Lp     Miles: 11.59
Work Order Date Contract Amount Estimated Completion Date
2006-02-14 $37,347,319 2009-01-22


Kcs (Mansfield) Dot No. 329-187l
025-05-0024-031 - Concrete new pavement
Proj. Engr: Stein, William     Route: US 171
Contractor: Best-Yet Builders, LLC     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2007-10-03 $100,456 2007-10-06


Kcs (Mansfield) Dot No. 329-187l
025-05-0024-032 - Concrete new pavement
Proj. Engr: Stein, William     Route: US 171
Contractor: Best-Yet Builders, LLC     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2007-10-03 $340,645 2007-10-06


Webster Parish

Note: The estimated completion date is based on the work order date and the contract days allowed.

Springhill - Jct. La 159 (Bridges)
084-03-0033 - Bridges reconditioned
Proj. Engr: North, David     Route: LA 157
Contractor: James Construction Group LLC     Miles: 1.25
Work Order Date Contract Amount Estimated Completion Date
2008-04-01 $11,612,059 2010-06-02


Junction La 157 to Arkansas State Line
086-02-0032 - Asphalt new pavement-new roadway/new alignments
Proj. Engr: North, David     Route:
Contractor: Benton & Brown, LLC.     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2009-08-10 $3,230,057 2010-06-29


Cotton Valley to Sarepta Passing Lanes
086-02-0038 - Asphalt widening and overlay
Proj. Engr: North, David     Route: US 371
Contractor: Madden Contracting Co., Inc.     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2010-01-04 $2,206,389 2010-06-25


Old Arcadia Road Bridges
713-14-0108 - New location/replacement of bridge
Proj. Engr: North, David     Route:
Contractor: Louisiana Bridge, Inc.     Miles: 0.23
Work Order Date Contract Amount Estimated Completion Date
2009-05-01 $1,105,319 2010-02-28


District 04

No districtwide projects.