LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT
Search Help

Projects Under Construction

District 02

    Updated 8 Feb 2010

Districtwide Projects

Jefferson Parish

Note: The estimated completion date is based on the work order date and the contract days allowed.

Huey P Long Bridge Widening (Wb, Eb Appr. & Br. Deck Widen.)
005-10-0037 - Bridges reconditioned
Proj. Engr: Todd, Timothy     Route: US 90
Contractor: Kiewit La/Massman/Traylor a Jt Ve     Miles: 4.91
Work Order Date Contract Amount Estimated Completion Date
2008-05-05 $435,384,174 2013-09-03


Huey P. Long Widening (Main Bridge - Substructure)
006-01-0012 - Bridges reconditioned
Proj. Engr: Todd, Timothy     Route: US 90
Contractor: Massman Construction Co.     Miles: 0.45
Work Order Date Contract Amount Estimated Completion Date
2006-04-10 $103,930,612 2009-09-14


Huey P. Long Bridge Widening (Main Span Superstructure)
006-01-0018 - Bridges reconditioned
Proj. Engr: Todd, Timothy     Route: US 90
Contractor: Massman/Traylor Bro/Ihi Inc Jt Ve     Miles: 0.45
Work Order Date Contract Amount Estimated Completion Date
2007-11-05 $452,121,618 2012-05-18


Jefferson Highway (Huey P. Long Bridge - Williams Blvd.)
006-30-0042 - Asphalt overlay of asphalt pavement
Proj. Engr: Duplantis, Michael     Route: LA 48
Contractor: Barriere Construction Co., LLC     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2009-08-13 $5,000,620 2010-02-14


Airline Dr. (North Broad - Labarre Road)
007-01-0023 - Asphalt overlay of asphalt pavement
Proj. Engr: Wetekamm, Fred     Route: US 61
Contractor: Barriere Construction Co., LLC     Miles: 3.86
Work Order Date Contract Amount Estimated Completion Date
2008-12-12 $4,281,498 2010-09-29


US 61 Signal Upgrades
007-02-0097 - Signalization
Proj. Engr: Perilloux, Steve     Route: US 61
Contractor: Jack B. Harper Contractor, Inc.     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
1990-09-03 $4,597,075 1992-01-05


LA 23 (Belle Chasse Hwy) & La 428 (Behrman Hwy) Signal Imp
062-01-0025 - Signalization
Proj. Engr: Capote, Nelson     Route: LA 23 LA 428
Contractor: Diamond Electrical Co., Inc.     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2008-02-25 $2,851,542 2009-06-24


LA 18 Widening (River Road to Highway 90)
063-04-0034 - Asphalt widening and overlay
Proj. Engr: Weber, Alan     Route: LA 18
Contractor: Barriere Construction Co., LLC.     Miles: 1.38
Work Order Date Contract Amount Estimated Completion Date
2009-06-11 $4,913,222 2009-12-11


Caminada Bay Bridge
064-01-0040 - New location/replacement of bridge
Proj. Engr: Gisclair, Gary     Route: LA 1
Contractor: Johnson Bros Corp-F Miller a J     Miles: 1.25
Work Order Date Contract Amount Estimated Completion Date
2009-09-25 $51,374,623 2012-05-11


LA Highway 45 (Barataria Boulevard) and Patriot Street
249-01-0045 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Capote, Nelson     Route: LA 45
Contractor: Hard Rock Construction Co.     Miles: 0.89
Work Order Date Contract Amount Estimated Completion Date
2006-09-23 $7,080,849 2007-07-03


Repair Damage to Walking Path Lights From Hurricane Katrina
283-08-0164 - Sidewalks/bike paths
Proj. Engr: Skoien, Richard W.     Route:
Contractor: Toomer Electrical Co., Inc.     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2007-03-05 $77,230 2007-09-10


Causeway Boulevard - 17th Street Canal
450-15-0089 - Asphalt widening and overlay
Proj. Engr: Standige, Frank H.     Route: I-10
Contractor: Boh Bros. Construction Co., LLC.     Miles: 1.92
Work Order Date Contract Amount Estimated Completion Date
2005-08-01 $74,454,760 2008-06-27


Causeway Boulevard Interchange (Phase I)
450-15-0100 - Concrete new pavement
Proj. Engr: Skoien, Richard     Route: I-10
Contractor: James Construction Group LLC     Miles: 0.29
Work Order Date Contract Amount Estimated Completion Date
2008-12-02 $32,630,099 2010-12-12


Causeway Boulevard Interchange (Phase Ii)
450-15-0103 - Concrete new pavement
Proj. Engr: Skoien, Richard     Route: I-10
Contractor: James Construction Group LLC     Miles: 0.70
Work Order Date Contract Amount Estimated Completion Date
2009-08-10 $50,988,401 2012-06-14


Permanent Repair to Federal Aid Eligible Roads
704-26-0011 - Miscellaneous
Proj. Engr: Chaudhry, Mohammad     Route:
Contractor: Boh Bros. Construction Co., LLC.     Miles: 1.26
Work Order Date Contract Amount Estimated Completion Date
2009-06-22 $957,238 2009-09-20


26th Street Bridge Over Canal No. 17 (Butler Canal)
713-26-0105 - New location/replacement of bridge
Proj. Engr: Luton, Loyd     Route:
Contractor: James Construction Group LLC     Miles: 0.02
Work Order Date Contract Amount Estimated Completion Date
2009-03-02 $1,116,881 2010-03-06


LA 45 to Bayou Barataria
826-10-0008 - Asphalt overlay of asphalt pavement
Proj. Engr: Capote, Nelson     Route: LA 560-4
Contractor: Boh Bros. Construction Co., Ll     Miles: 0.89
Work Order Date Contract Amount Estimated Completion Date
2009-05-15 $323,659 2009-07-10


Lafourche Parish

Note: The estimated completion date is based on the work order date and the contract days allowed.

Bayou Lafourche Bridge at Larose
064-05-0085 - New location/replacement of bridge
Proj. Engr: Langenstein, Larry     Route: LA 1 LA 308 LA 657 LA 310
Contractor: James Construction Group LLC     Miles: 1.20
Work Order Date Contract Amount Estimated Completion Date
2009-06-15 $30,442,823 2012-06-05


Fourchon to Leeville Bridge (Phase 1a)
064-30-0035 - Asphalt widening and overlay
Proj. Engr: Gisclair, Gary     Route: LA 3090 LA 1
Contractor: James Construction Group LLC     Miles: 5.34
Work Order Date Contract Amount Estimated Completion Date
2007-03-19 $138,434,740 2011-11-09


Gustav Repairs to La 3090
064-30-0038 - Asphalt overlay of asphalt pavement
Proj. Engr: Rogers, Chris     Route: LA 3090
Contractor: Barriere Construction Co., LLC     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2009-11-25 $680,801 2010-03-07


St. Charles Bridge - La 20
407-04-0041 - Asphalt overlay of asphalt pavement
Proj. Engr: Rogers, Chris     Route: LA 308
Contractor: Huey Stockstill, Inc.     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2009-09-30 $1,993,787 2010-05-31


LA 3235 Cross Drains (Cm)
829-26-0013 - Drainage
Proj. Engr: Weber, Alan     Route:
Contractor: Barriere Construction Co., LLC     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2006-07-05 $71,702 2006-09-24


LA 1 Relocated - Port Fourchon to Leeville - Phase 1b
829-32-0007 - New location/replacement of moveable bridge
Proj. Engr: Gisclair, Gary     Route: LA 1
Contractor: Traylor Bro/Massman Const a Jt Ve     Miles: 4.01
Work Order Date Contract Amount Estimated Completion Date
2006-03-01 $145,285,671 2014-05-27


LA 1 Over Bayou Lafourche at Leeville, Phase 1c - Main Spans
829-32-0008 - New location/replacement of bridge
Proj. Engr: Gisclair, Gary     Route: LA 1
Contractor: Traylor Bro/Massman Const a Jt Ve     Miles: 0.17
Work Order Date Contract Amount Estimated Completion Date
2006-06-01 $21,669,398 2009-05-30


Orleans Parish

Note: The estimated completion date is based on the work order date and the contract days allowed.

N. Broad - W. End Inner Harbor Bridge
006-03-0057 - Asphalt overlay of asphalt pavement
Proj. Engr: Wetekamm, Fred     Route: US 90
Contractor: Barriere Construction Co., LLC     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2009-08-10 $3,964,599 2010-04-30


Danziger Movable Bridge Repairs
006-90-0096 - Moveable bridges reconditioned
Proj. Engr: Guidry, John     Route: US 90
Contractor: Coastal Bridge Co., L.L.C.     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2009-07-03 $823,000 2009-12-31


Airline Dr. (North Broad - Labarre Road)
007-01-0023 - Asphalt overlay of asphalt pavement
Proj. Engr: Wetekamm, Fred     Route: US 61
Contractor: Barriere Construction Co., LLC     Miles: 3.86
Work Order Date Contract Amount Estimated Completion Date
2008-12-12 $4,281,498 2010-09-29


Jackson Barracks Median Crossovers
046-02-0025 - Asphalt new pavement-new roadway/new alignments
Proj. Engr: Wetekamm, Fred     Route: LA 46
Contractor: Three C's Properties Inc     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2009-10-30 $141,450 2010-01-09


Judge Seeber Bridge Repairs
046-31-0053 - Moveable bridges reconditioned
Proj. Engr: Guidry, John     Route: LA 39
Contractor: Boh Bros. Construction Co., LLC.     Miles: 0.07
Work Order Date Contract Amount Estimated Completion Date
2009-06-26 $6,952,134 2010-04-24


LA 23 (Belle Chasse Hwy) & La 428 (Behrman Hwy) Signal Imp
062-01-0025 - Signalization
Proj. Engr: Capote, Nelson     Route: LA 23 LA 428
Contractor: Diamond Electrical Co., Inc.     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2008-02-25 $2,851,542 2009-06-24


Repair Damage to Walking Path Lights From Hurricane Katrina
283-08-0164 - Sidewalks/bike paths
Proj. Engr: Skoien, Richard W.     Route:
Contractor: Toomer Electrical Co., Inc.     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2007-03-05 $77,230 2007-09-10


Roundabout Woodland Highway at La 407
409-02-0016 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Capote, Nelson     Route: LA 406 LA 407
Contractor: Three C's Properties Inc     Miles: 0.15
Work Order Date Contract Amount Estimated Completion Date
2009-12-03 $749,885 2010-04-04


I-10 Bridge Over Lake Pontchartrain
450-17-0025 - New location/replacement of bridge
Proj. Engr: Zzzz Horn, John     Route: I-10
Contractor:     Miles: 5.26
Work Order Date Contract Amount Estimated Completion Date
2006-06-01 $432,892,046 2012-06-18


Acrow Disassembly, Transportation, Relocation, and Storage
450-17-0032 - Bridge removal
Proj. Engr: Horn, John     Route: I-10
Contractor: Boh Bros. Construction Co., LLC.     Miles: 5.41
Work Order Date Contract Amount Estimated Completion Date
2009-08-03 $4,296,445 2010-02-21


Permanent and Maintenance Fence Repairs
450-34-0094 - Fencing
Proj. Engr: Wetekamm, Fred     Route: I-610
Contractor: Three C's Properties Inc     Miles: 0.85
Work Order Date Contract Amount Estimated Completion Date
2008-10-20 $481,148 2009-03-21


Paris Rd to C.S.L.M. 21.24
450-90-0162 - Concrete pavement rehab-grinding/dowell retrofit/should drain install
Proj. Engr: Wetekamm, Fred     Route: I-10
Contractor: Barriere Construction Co., LLC     Miles: 4.45
Work Order Date Contract Amount Estimated Completion Date
2009-02-09 $17,820,454 2011-01-07


I-10 East Safety & Beautification, Phase II
450-90-0194 - Landscaping
Proj. Engr: Wetekamm, Fred     Route: I-10
Contractor: Twin Shores Lands. & Const Ser     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2009-09-23 $860,745 2010-05-14


Pontchartrain Pump Station Repairs Due to Hurricane Katrina
450-90-0210 - Drainage
Proj. Engr: Wetekamm, Fred     Route: I-10
Contractor: Industrial & Mechanical Contr. Ll     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2008-08-04 $1,597,784 2009-10-04


Administration Building Expansion
610-01-0022 - Buildings and grounds excluding rest areas
Proj. Engr: Skoien, Richard W.     Route:
Contractor: Jaroy Construction, Inc.     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2008-02-11 $3,799,661 2009-09-10


Permanent Repair to Federal Aid Eligible Roads
704-36-0027 - Miscellaneous
Proj. Engr: Chaudhry, Mohammad     Route:
Contractor: Barriere Construction Co., LLC     Miles: 2.73
Work Order Date Contract Amount Estimated Completion Date
2009-04-29 $4,876,494 2010-05-07


Permanent Repair to Federal Aid Eligible Roads
704-36-0028 - Miscellaneous
Proj. Engr: Chaudhry, Mohammad     Route:
Contractor: Barriere Construction Co., LLC     Miles: 1.70
Work Order Date Contract Amount Estimated Completion Date
2009-07-06 $5,188,873 2010-04-06


Permanent Repair to Federal Aid Eligible Roads
704-36-0032 - Miscellaneous
Proj. Engr: Chaudhry, Mohammad     Route:
Contractor: Rmd Holdings Ltd     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2009-11-20 $18,206,492 2011-05-15


Permanent Repair to Federal Aid Eligible Roads
704-36-0039 - Miscellaneous
Proj. Engr: Chaudhry, Mohammad     Route:
Contractor: Barriere Construction Co., LLC     Miles: 7.46
Work Order Date Contract Amount Estimated Completion Date
2009-08-14 $9,526,928 2010-03-27


Permanent Repair to Federal Aid Eligible Roads
704-36-0040 - Miscellaneous
Proj. Engr: Koutnik, William     Route:
Contractor: Hard Rock Construction Co.     Miles: 2.21
Work Order Date Contract Amount Estimated Completion Date
2010-01-08 $6,992,652 2010-07-16


Permanent Repair to Federal Aid Eligible Roads
704-36-0042 - Miscellaneous
Proj. Engr: Chaudhry, Mohammad     Route:
Contractor: Boh Bros. Construction Co., Ll     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2009-12-17 $9,794,401 2010-06-29


Permanent Repair to Federal Aid Eligible Roads
704-36-0046 - Miscellaneous
Proj. Engr: Chaudhry, Mohammad     Route:
Contractor: Boh Bros. Construction Co., LLC.     Miles: 0.38
Work Order Date Contract Amount Estimated Completion Date
2009-07-06 $1,023,331 2009-11-27


Permanent Repair to Federal Aid Eligible Roads
704-36-0047 - Miscellaneous
Proj. Engr: Chaudhry, Mohammad     Route:
Contractor: Barriere Construction Co., LLC     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2009-10-06 $4,451,740 2010-06-04


Permanent Repair to Federal Aid Eligible Roads
704-36-0049 - Miscellaneous
Proj. Engr: Chaudhry, Mohammad     Route:
Contractor: Boh Bros. Construction Co., LLC.     Miles: 1.36
Work Order Date Contract Amount Estimated Completion Date
2009-07-10 $2,655,539 2010-02-12


Permanent Repair to Federal Aid Eligible Roads
704-36-0050 - Miscellaneous
Proj. Engr: Chaudhry, Mohammad     Route:
Contractor: Boh Bros. Construction Co., Ll     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2009-10-12 $15,031,480 2010-09-07


Permanent Repair to Federal Aid Eligible Roads
704-36-0068 - Miscellaneous
Proj. Engr: Chaudhry, Mohammad     Route:
Contractor: Barriere Construction Co., LLC     Miles: 2.52
Work Order Date Contract Amount Estimated Completion Date
2009-06-03 $6,060,619 2010-09-01


Bayou St. John (Park Island)
713-36-0100 - New location/replacement of bridge
Proj. Engr: Heyman, Many     Route:
Contractor: Cycle Construction Co. L.L.C.     Miles: 0.05
Work Order Date Contract Amount Estimated Completion Date
2009-12-07 $1,988,131 2010-07-31


Michoud Boulevard Bridge(North and South Bound)
713-36-0103 - New location/replacement of bridge
Proj. Engr: Wetekamm, Fred     Route:
Contractor: Boh Bros. Construction Co., LLC.     Miles: 0.24
Work Order Date Contract Amount Estimated Completion Date
2007-08-01 $3,977,437 2009-02-15


Algiers Cut Off Canal Bridge Lighting Installation
836-08-0072 - Roadway lighting
Proj. Engr: Capote, Nelson     Route: LA 407
Contractor: Jack B. Harper Contractor, Inc.     Miles: 1.19
Work Order Date Contract Amount Estimated Completion Date
2008-02-01 $885,381 2008-08-20


Plaquemines Parish

Note: The estimated completion date is based on the work order date and the contract days allowed.

LA 23 (Belle Chasse Hwy) & La 428 (Behrman Hwy) Signal Imp
062-01-0025 - Signalization
Proj. Engr: Capote, Nelson     Route: LA 23 LA 428
Contractor: Diamond Electrical Co., Inc.     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2008-02-25 $2,851,542 2009-06-24


Belle Chasse Tunnel Rehabilitation
062-02-0120 - Miscellaneous
Proj. Engr: Capote, Nelson     Route: LA 23
Contractor: Grady Crawford Const. Co., Inc     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2009-12-21 $2,134,438 2010-08-20


Emergency Dredging of Ostrica Canal
704-38-0011 - Miscellaneous
Proj. Engr: Capote, Nelson     Route:
Contractor: Grillot Construction LLC     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2008-02-11 $1,058,050 2008-11-23


Doullut Canal Bridge
713-38-0001 - New location/replacement of bridge
Proj. Engr: Capote, Nelson     Route:
Contractor: Coastal Bridge Co., L.L.C.     Miles: 0.20
Work Order Date Contract Amount Estimated Completion Date
2008-03-03 $10,878,834 2010-03-31


St. Bernard Parish

Note: The estimated completion date is based on the work order date and the contract days allowed.

St. Bernard Highway Drainage Improvements Phase II
046-03-0070 - Miscellaneous
Proj. Engr: Wetekamm, Fred     Route: LA 46
Contractor: Boh Bros. Construction Co., LLC.     Miles: 2.90
Work Order Date Contract Amount Estimated Completion Date
2008-03-17 $3,142,604 2009-01-28


Judge Perez (Guerenger Canal to Paris Rd.)
046-32-0037 - Asphalt overlay of asphalt pavement
Proj. Engr: Wetekamm, Fred     Route: LA 39
Contractor: Rcs Contractors, Inc.     Miles: 2.01
Work Order Date Contract Amount Estimated Completion Date
2009-05-01 $821,431 2009-10-10


Paris Road (Virtue - Bayou Bienvenue)
148-01-0028 - Concrete pavement rehab-grinding/dowell retrofit/should drain install
Proj. Engr: Wetekamm, Fred     Route: LA 47
Contractor: Barriere Construction Co., LLC     Miles: 1.94
Work Order Date Contract Amount Estimated Completion Date
2009-01-21 $1,378,369 2009-04-23


Yscloskey Bridge Rehabilitation- Hurricane Katrina
284-02-0035 - Moveable bridges reconditioned
Proj. Engr: Wetekamm, Fred     Route:
Contractor: Coastal Bridge Co., L.L.C.     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2007-01-22 $2,495,305 2008-01-20


Permanent Repair to Federal Aid Eligible Roads
704-44-0012 - Miscellaneous
Proj. Engr: Wetekamm, Fred     Route:
Contractor: Boh Bros. Construction Co., LLC.     Miles: 2.21
Work Order Date Contract Amount Estimated Completion Date
2009-08-05 $4,257,165 2010-12-23


Permanent Repair to Federal Aid Eligible Roads
704-44-0014 - Miscellaneous
Proj. Engr: Koutnik, William     Route:
Contractor: Barriere Construction Co., LLC     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2010-02-01 $2,504,722 2010-07-22


St. Charles Parish

Note: The estimated completion date is based on the work order date and the contract days allowed.

US 61 Signal Upgrades
007-02-0097 - Signalization
Proj. Engr: Perilloux, Steve     Route: US 61
Contractor: Jack B. Harper Contractor, Inc.     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
1990-09-03 $4,597,075 1992-01-05


US 61 Barrier System
007-03-0056 - Guardrails
Proj. Engr: Duplantis, Michael     Route: US 61
Contractor: Rmd Holdings Ltd     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2009-07-19 $1,599,521 2010-04-04


LA 48 at La 50 Intersection Improvements
282-02-0046 - Asphalt overlay of asphalt pavement
Proj. Engr: Duplantis, Michael     Route: LA 48 LA 50
Contractor: Byron E. Talbot Contractor, Inc.     Miles: 1.10
Work Order Date Contract Amount Estimated Completion Date
2009-02-09 $1,267,882 2009-09-10


Miss. River Bridge(Luling) Deck Test Section & Joint Repairs
450-37-0020 - Bridges reconditioned
Proj. Engr: Hansen, Osmond     Route: I-310
Contractor: Boh Bros. Construction Co., LLC.     Miles: 0.52
Work Order Date Contract Amount Estimated Completion Date
2004-09-10 $1,213,927 2004-11-12


Mississippi River Bridge (Luling) Cable Stay Replacement
450-37-0022 - Bridges reconditioned
Proj. Engr: Weber, Alan     Route: I-310
Contractor: Kiewit Louisiana Co     Miles: 1.16
Work Order Date Contract Amount Estimated Completion Date
2009-05-15 $30,524,749 2011-02-25


S. End Miss. River Br. - US 90
450-38-0022 - Asphalt overlay of asphalt pavement
Proj. Engr: Weber, Alan     Route: I-310
Contractor: Barriere Construction Co., LLC     Miles: 4.09
Work Order Date Contract Amount Estimated Completion Date
2008-09-22 $2,020,179 2009-07-02


Terrebonne Parish

Note: The estimated completion date is based on the work order date and the contract days allowed.

Johnson Ridge Sidewalk
065-04-0041 - Sidewalks/bike paths
Proj. Engr: Picciola, Joe     Route: LA 24
Contractor: Rmd Holdings Ltd     Miles: 1.39
Work Order Date Contract Amount Estimated Completion Date
2009-02-02 $241,784 2009-06-04


Bayou Terrebonne Bridge and Approaches
065-91-0016 - Asphalt widening and overlay
Proj. Engr: Rogers, Chris     Route: LA 24
Contractor: James Construction Group LLC     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2009-11-24 $26,679,003 2012-04-13


LA 316 Shoulder Widening and Drainage
412-04-0013 - Asphalt widening and overlay
Proj. Engr: Rogers, Chris     Route: LA 316
Contractor: LA Contracting Enterprises LLC     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2009-10-23 $421,016 2010-04-13


District 02

No districtwide projects.