Projects Under Construction
District 03
Updated 2 Jul 2009
Districtwide Projects
Acadia Parish
Note: The estimated completion date is based
on the work order date and the contract days
allowed.
|
Hist. Parkerson Ave. Redevelopment-First St. to Court Circle |
| 057-02-0028 - Miscellaneous |
| Proj. Engr: Oliver Jr., William J. |
Route: LA 13 |
| Contractor: Merrick Construction Co. |
Miles: 0.44 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2008-06-02 |
$4,982,628 |
2010-03-04 |
|
Bayou Plaquemine Bridge and Approaches |
| 057-03-0039 - New location/replacement of bridge |
| Proj. Engr: Oliver Jr., William J. |
Route: LA 13 |
| Contractor: James Construction Group LLC |
Miles: 0.62 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2007-03-12 |
$7,305,940 |
2008-11-25 |
|
South Court Circle - Northern Avenue |
| 057-03-0050 - Asphalt overlay of asphalt pavement |
| Proj. Engr: Oliver Jr., William J. |
Route: LA 13 |
| Contractor: Diamond B Construction Co., L.L.C |
Miles: 0.68 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2008-12-18 |
$1,101,529 |
2009-04-29 |
|
Egan Jct. Local Rd. - N. Jct. La 98 |
| 210-01-0011 - Asph concrete ovly over in place stabilized/cement treated base course |
| Proj. Engr: Oliver Jr., William J. |
Route: LA 91 |
| Contractor: W. E. Mcdonald & Son, LLC. |
Miles: 7.36 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2009-04-01 |
$3,859,083 |
2010-01-09 |
|
I-10 Pavement Marking Replacement East and West Bound Lanes |
| 450-04-0097 - Striping and pavement markers |
| Proj. Engr: Landry, David N. |
Route: I-10 |
| Contractor: Highway Technologies Inc |
Miles: 51.07 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2009-05-19 |
$179,304 |
2009-07-26 |
Evangeline Parish
Note: The estimated completion date is based
on the work order date and the contract days
allowed.
|
I-49 Pavement Marking Replacement |
| 455-04-0021 - Striping and pavement markers |
| Proj. Engr: Vollman, Wayne C. |
Route: I-49 |
| Contractor: Highway Graphics Inc. |
Miles: 65.90 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2009-05-22 |
$361,374 |
2009-07-17 |
|
LA 1169 - St. Landry Parish Line |
| 820-03-0011 - Asph concrete ovly over in place stabilized/cement treated base course |
| Proj. Engr: Fontenot, John B. |
Route: LA 748 |
| Contractor: W. E. Mcdonald & Son, LLC. |
Miles: 2.44 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2009-04-15 |
$1,215,305 |
2009-09-04 |
|
Jct. La 104 - Jct. La 29 |
| 820-29-0003 - Asphalt Pavement Rehabilitation |
| Proj. Engr: Fontenot, John B. |
Route: LA 1161 |
| Contractor: W. E. Mcdonald & Son, LLC. |
Miles: 7.12 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2008-08-11 |
$4,102,493 |
2009-04-01 |
Iberia Parish
Note: The estimated completion date is based
on the work order date and the contract days
allowed.
|
Conversion of Conventional End Wedge System to Roller Wedge |
| 207-01-0059 - Moveable bridges reconditioned |
| Proj. Engr: Begnaud, Jerry |
Route: LA 82 LA 86 LA 320 LA 344 LA 3069 |
| Contractor: C.E.C., Inc. |
Miles: 0.00 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2007-03-01 |
$501,542 |
2008-08-22 |
|
US 90 Interchange at La 675 |
| 424-04-0034 - New location/replacement of bridge |
| Proj. Engr: Borazjani, Mohammad |
Route: US 90 |
| Contractor: James Construction Group LLC |
Miles: 1.76 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2006-11-17 |
$22,870,243 |
2009-04-19 |
|
LA 14 to La 83 |
| 424-04-0048 - Signing |
| Proj. Engr: Borazjani, Mohammad |
Route: US 90 |
| Contractor: Alpha Service and Products, Inc. |
Miles: 6.15 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2008-03-10 |
$686,854 |
2009-02-19 |
|
US 90 Frontage Roads (La 675 - La 88) |
| 424-04-0051 - Asphalt new pavement-new roadway/new alignments |
| Proj. Engr: Borazjani, Mohammad |
Route: US 90 |
| Contractor: H & S Construction Co., Inc. |
Miles: 3.05 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2009-02-06 |
$10,711,836 |
2009-12-06 |
|
US 90 Interchange @ La 675 Signing |
| 424-04-0058 - Signing |
| Proj. Engr: Borazjani, Mohammad |
Route: US 90 |
| Contractor: Glover Enterprises, Inc. |
Miles: 3.41 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2009-06-01 |
$229,596 |
2010-03-11 |
Lafayette Parish
Note: The estimated completion date is based
on the work order date and the contract days
allowed.
|
Ambassador Caffery Parkway (Verot School Rd. - U.S. 90) |
| 216-03-0032 - Asphalt widening and overlay |
| Proj. Engr: Faust, Jeff |
Route: LA 3073 LA 339 LA 89 US 90 |
| Contractor: Gilchrist Construction Co. LLC |
Miles: 7.39 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2007-10-22 |
$44,802,311 |
2012-10-11 |
|
I-10 Pavement Marking Replacement East and West Bound Lanes |
| 450-04-0097 - Striping and pavement markers |
| Proj. Engr: Landry, David N. |
Route: I-10 |
| Contractor: Highway Technologies Inc |
Miles: 51.07 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2009-05-19 |
$179,304 |
2009-07-26 |
|
I-10 @ Louisiana Avenue-Interchange Lighting |
| 450-05-0055 - Roadway lighting |
| Proj. Engr: Landry, David N. |
Route: I-10 |
| Contractor: Jack B. Harper Contractor, Inc. |
Miles: 1.71 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2008-12-11 |
$873,939 |
2009-11-03 |
|
(Jct. I-10 to La 103) |
| 455-01-0048 - Signing |
| Proj. Engr: Landry, David N. |
Route: I-49 |
| Contractor: Atwood Fence Company Inc. |
Miles: 25.47 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2009-01-05 |
$5,158,078 |
2011-03-27 |
St. Landry Parish
Note: The estimated completion date is based
on the work order date and the contract days
allowed.
|
US 190 Over US 71 Bridge Rehabilitation |
| 008-04-0060 - Bridges reconditioned |
| Proj. Engr: Fontenot, John B. |
Route: US 190 |
| Contractor: Coastal Bridge Co., L.L.C. |
Miles: 0.57 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2007-12-26 |
$4,421,796 |
2009-09-22 |
|
Jct. US 167 - Jct. US 190 |
| 066-08-0012 - Asphalt widening and overlay |
| Proj. Engr: Fontenot, John B. |
Route: US 167 LA 749 |
| Contractor: Gilchrist Construction Co. LLC |
Miles: 4.27 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2008-01-22 |
$9,001,493 |
2009-06-26 |
|
Drainage Canal Bridges on La 35 |
| 207-09-0011 - New location/replacement of bridge |
| Proj. Engr: Fontenot, John B. |
Route: LA 35 |
| Contractor: H & S Construction Co., Inc. |
Miles: 0.20 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2008-10-27 |
$1,334,905 |
2009-04-21 |
|
3.59 Miles South of Jct US 190 - Jct US 190 |
| 208-02-0014 - Asphalt overlay of asphalt pavement |
| Proj. Engr: Fontenot, John B. |
Route: LA 357 |
| Contractor: Prairie Contractors Inc. |
Miles: 3.59 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2009-03-23 |
$1,697,379 |
2009-07-13 |
|
Drainage Canal Bridge |
| 380-02-0007 - New location/replacement of bridge |
| Proj. Engr: Fontenot, John B. |
Route: LA 363 |
| Contractor: Guinn Brothers, LLC. |
Miles: 0.15 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2009-01-12 |
$1,462,293 |
2010-01-05 |
|
Bayou Courtableau Bridge |
| 380-03-0013 - New location/replacement of bridge |
| Proj. Engr: Fontenot, John B. |
Route: LA 103 |
| Contractor: Gilchrist Construction Co. LLC |
Miles: 0.34 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2008-12-22 |
$3,476,297 |
2010-01-10 |
|
(Jct. I-10 to La 103) |
| 455-01-0048 - Signing |
| Proj. Engr: Landry, David N. |
Route: I-49 |
| Contractor: Atwood Fence Company Inc. |
Miles: 25.47 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2009-01-05 |
$5,158,078 |
2011-03-27 |
St. Martin Parish
Note: The estimated completion date is based
on the work order date and the contract days
allowed.
|
I-10 Pavement Marking Replacement East and West Bound Lanes |
| 450-04-0097 - Striping and pavement markers |
| Proj. Engr: Landry, David N. |
Route: I-10 |
| Contractor: Highway Technologies Inc |
Miles: 51.07 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2009-05-19 |
$179,304 |
2009-07-26 |
|
I-10 Pavement Marking Replacement |
| 450-06-0063 - Striping and pavement markers |
| Proj. Engr: Palermo, Keith |
Route: I-10 |
| Contractor: Highway Technologies Inc |
Miles: 36.11 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2009-05-19 |
$524,128 |
2009-11-06 |
|
Breaux Bridge Weigh Station Improvements |
| 693-09-0009 - Buildings and grounds excluding rest areas |
| Proj. Engr: Landry, David N. |
Route: I-10 |
| Contractor: Diamond Electrical Co., Inc. |
Miles: 0.00 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2009-04-29 |
$147,371 |
2009-08-28 |
|
Jct La 347 - W End Bayou Mersier Bridge |
| 850-08-0009 - Asph concrete ovly over in place stabilized/cement treated base course |
| Proj. Engr: Landry, David N. |
Route: LA 352 |
| Contractor: F.G. Sullivan, Jr. Contractor LLC |
Miles: 2.62 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2009-01-26 |
$2,084,889 |
2009-07-07 |
St. Mary Parish
Note: The estimated completion date is based
on the work order date and the contract days
allowed.
|
Jct La 322 - C.S.L.M. 0.764 |
| 004-06-0032 - Asphalt overlay of concrete pavement |
| Proj. Engr: Lissard, Chris |
Route: LA 182 |
| Contractor: H & S Construction Co., Inc. |
Miles: 1.16 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2008-12-15 |
$758,905 |
2009-02-24 |
|
Conversion of Conventional End Wedge System to Roller Wedge |
| 207-01-0059 - Moveable bridges reconditioned |
| Proj. Engr: Begnaud, Jerry |
Route: LA 82 LA 86 LA 320 LA 344 LA 3069 |
| Contractor: C.E.C., Inc. |
Miles: 0.00 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2007-03-01 |
$501,542 |
2008-08-22 |
Vermilion Parish
Note: The estimated completion date is based
on the work order date and the contract days
allowed.
|
Conversion of Conventional End Wedge System to Roller Wedge |
| 207-01-0059 - Moveable bridges reconditioned |
| Proj. Engr: Begnaud, Jerry |
Route: LA 82 LA 86 LA 320 LA 344 LA 3069 |
| Contractor: C.E.C., Inc. |
Miles: 0.00 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2007-03-01 |
$501,542 |
2008-08-22 |
|
Jct La 14 to Jct La 699 |
| 393-01-0006 - Asph concrete ovly over in place stabilized/cement treated base course |
| Proj. Engr: Begnaud, Jerry |
Route: LA 343 |
| Contractor: H & S Construction Co., Inc. |
Miles: 6.13 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2009-02-25 |
$3,181,147 |
2009-08-26 |
|
Cameron Parish Line - Junction La 35 |
| 705-57-0014 - Miscellaneous |
| Proj. Engr: Begnaud, Jerry |
Route: LA 82 |
| Contractor: |
Miles: 30.85 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2008-05-16 |
$7,014,670 |
2009-03-09 |
|
Bridges In Vermillion Parish |
| 713-57-0105 - New location/replacement of bridge |
| Proj. Engr: Begnaud, Jerry |
Route: |
| Contractor: Guinn Brothers, LLC. |
Miles: 0.03 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2009-02-25 |
$1,723,345 |
2010-04-29 |
|
C.S.L.M. 0.000 - C.S.L.M. 5.844 |
| 857-66-0010 - Asphalt surface treatment |
| Proj. Engr: Begnaud, Jerry |
Route: LA 3147 |
| Contractor: M. Matt Durand, LLC |
Miles: 5.84 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2009-06-10 |
$2,097,004 |
2009-12-04 |
District 03
No districtwide projects.
DOTD Home Page
|