Projects Under Construction
District 03
Updated 19 Jun 2013
Districtwide Projects
Acadia Parish
Note: The estimated completion date is based
on the work order date and the contract days
allowed.
|
LA 1120: La 100 - La 98 |
| H.007837.6 - Asph concrete ovly over in place stabilized/cement treated base course |
| Proj. Engr: Faust, Jeff |
Route: LA 1120 |
| Contractor: Coastal Bridge Co., L.L.C. |
Miles: 6.22 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2013-01-02 |
$3,272,185 |
2013-07-03 |
Evangeline Parish
Note: The estimated completion date is based
on the work order date and the contract days
allowed.
|
Bridge Over Prong Bayou |
| H.006105.6 - New location/replacement of bridge |
| Proj. Engr: Chachere, Nicholas |
Route: |
| Contractor: Guinn Services, LLC |
Miles: 0.00 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2013-02-04 |
$383,781 |
2013-08-25 |
Iberia Parish
Note: The estimated completion date is based
on the work order date and the contract days
allowed.
|
US 90 - Jct. La 182 |
| H.002760.6-R1 - Asphalt new pavement-new roadway/new alignments |
| Proj. Engr: Deblanc, Frank |
Route: LA 668 LA 671 |
| Contractor: Gilchrist Construction Co. LLC |
Miles: 0.20 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2013-02-27 |
$8,385,219 |
2015-10-14 |
|
US 90 Frontage Roads: Darnall Rd. - La 85 |
| H.002890.6 - Asphalt new pavement-new roadway/new alignments |
| Proj. Engr: Arceneaux, Mark |
Route: US 90 |
| Contractor: Gilchrist Construction Co. LLC |
Miles: 2.97 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2012-07-27 |
$5,826,531 |
2013-10-04 |
|
Daspit Elementary School Sidewalk Project |
| H.006508.6 - Sidewalks/bike paths |
| Proj. Engr: Sanford, Kristi |
Route: |
| Contractor: Southern Constructors, LLC |
Miles: 0.00 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2012-06-11 |
$141,475 |
2012-11-12 |
|
Jeanerette Movable Bridge Electrical and Mechanical Repairs |
| 241-01-0015 - Moveable bridges reconditioned |
| Proj. Engr: Arceneaux, Mark |
Route: |
| Contractor: Coastal Bridge Co., L.L.C. |
Miles: 0.00 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2010-08-11 |
$504,342 |
2011-01-09 |
|
US 90 Frontage Roads (La 83 - Darnall Rd.) |
| 424-04-0052 - Asphalt new pavement-new roadway/new alignments |
| Proj. Engr: Arceneaux, Mark |
Route: |
| Contractor: Gilchrist Construction Co. LLC |
Miles: 2.08 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2010-02-25 |
$6,187,202 |
2011-10-25 |
|
Bayou Teche Bridge (Jefferson St.) |
| 823-42-0005 - New location/replacement of bridge |
| Proj. Engr: Arceneaux, Mark |
Route: |
| Contractor: Cecil D. Gassiott, LLC |
Miles: 0.10 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2010-08-30 |
$7,348,696 |
2013-07-30 |
Lafayette Parish
Note: The estimated completion date is based
on the work order date and the contract days
allowed.
|
Roundabout at Inter. La 93 & La 3168 |
| H.002158.6 - Concrete new pavement |
| Proj. Engr: Landry, David N. |
Route: LA 93 |
| Contractor: Richard Price Contracting Co, |
Miles: 0.01 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2012-11-05 |
$2,325,496 |
2013-07-06 |
|
Lafayette Mpo Non State Pvt Marking |
| H.007230.6 - Striping and pavement markers |
| Proj. Engr: Cole, Chris |
Route: |
| Contractor: Southern Synergy LLC |
Miles: 0.00 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2013-03-18 |
$412,249 |
2013-08-17 |
|
US 90: Right Turn @ La 93 |
| H.009303.6 - Traffic flow improvements - formerly turn lanes |
| Proj. Engr: Landry, David N. |
Route: US 90 |
| Contractor: Glenn Lege Construction Inc |
Miles: 0.13 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2012-09-24 |
$618,178 |
2013-02-03 |
|
LA 182: Billeaud Overpass - St Martin P/L |
| H.009773.6 - Asphalt overlay of asphalt pavement |
| Proj. Engr: Faust, Jeff |
Route: LA 182 |
| Contractor: Diamond B Construction Co., L. |
Miles: 0.94 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2012-09-26 |
$184,163 |
2012-12-06 |
|
District 03 Laboratory Chiller Replacement |
| H.971963.6 - Buildings and grounds excluding rest areas |
| Proj. Engr: Landry, David N. |
Route: |
| Contractor: Bernhard Mechanical Contractor |
Miles: 0.00 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2012-12-18 |
$98,035 |
2013-03-31 |
|
Carencro La 182 Multi-Use Path, Phase II |
| 032-01-0035 - Sidewalks/bike paths |
| Proj. Engr: Hoppe, Pete |
Route: LA 182 |
| Contractor: Beard Construction Group LLC |
Miles: 0.76 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2009-10-19 |
$305,763 |
2010-03-10 |
|
US 90 Pinhook to Broussard |
| 424-02-0088-R1 - Miscellaneous |
| Proj. Engr: Faust, Jeff |
Route: US 90 |
| Contractor: Diamond B Construction Co., L. |
Miles: 7.40 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2010-03-02 |
$22,224,701 |
2012-09-15 |
|
Verot School Rd(C&g)&digby,Pillette,&lozes Outfall Drain Imp |
| 828-12-0021-R1 - Clearing and grubbing |
| Proj. Engr: Faust, Jeff |
Route: LA 339 |
| Contractor: Rmd Holdings Ltd |
Miles: 3.19 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2011-09-11 |
$12,712,103 |
2015-02-27 |
St. Landry Parish
Note: The estimated completion date is based
on the work order date and the contract days
allowed.
|
Bayou Plaquemine Bridge |
| H.002104.6 - New location/replacement of bridge |
| Proj. Engr: Fontenot, John B. |
Route: LA 104 |
| Contractor: Guinn Services, LLC |
Miles: 0.40 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2012-11-26 |
$832,409 |
2013-06-02 |
|
LA 93: N. C/L Cankton - La 182 |
| H.002161.6 - Asph concrete ovly over in place stabilized/cement treated base course |
| Proj. Engr: Fontenot, John B. |
Route: LA 93 |
| Contractor: Diamond B Construction Co., L. |
Miles: 5.22 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2012-11-19 |
$3,894,451 |
2013-05-16 |
|
Grand Prairie Rest Area Improvements |
| H.003691.6-R1 - Rest areas |
| Proj. Engr: Chachere, Nicholas |
Route: |
| Contractor: Quality Design & Construction, |
Miles: 0.00 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2013-03-11 |
$2,395,000 |
2013-11-18 |
|
Eunice East Elementary Sidewalk Project |
| H.007337.6 - Sidewalks/bike paths |
| Proj. Engr: Liang, Frank |
Route: |
| Contractor: Jd's Rebar & Construction Inc. |
Miles: 0.00 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2012-06-25 |
$58,114 |
2012-09-25 |
|
LA 360: La 10 - La 105 |
| H.008331.6 - Asph concrete ovly over in place stabilized/cement treated base course |
| Proj. Engr: Fontenot, John B. |
Route: LA 360 |
| Contractor: W. E. Mcdonald & Son, LLC. |
Miles: 8.35 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2013-02-21 |
$5,302,666 |
2014-01-21 |
|
District 03 Controller Upgrade |
| H.010477.6 - Signalization |
| Proj. Engr: Chachere, Nicholas |
Route: US 190 |
| Contractor: Ernest P. Breaux Electrical, I |
Miles: 0.10 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2013-05-03 |
$812,700 |
2013-11-01 |
St. Martin Parish
Note: The estimated completion date is based
on the work order date and the contract days
allowed.
|
LA 92: La 182 - La 31 |
| H.002147.6 - Asph concrete ovly over in place stabilized/cement treated base course |
| Proj. Engr: Landry, David N. |
Route: LA 92 |
| Contractor: Glenn Lege Construction Inc |
Miles: 4.26 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2012-05-02 |
$2,633,398 |
2012-10-11 |
|
Butte Larose Rest Area Improvements |
| H.003678.6-R1 - Rest areas |
| Proj. Engr: Landry, David N. |
Route: |
| Contractor: Bulliard Construction Co. Inc. |
Miles: 0.00 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2013-02-13 |
$3,839,000 |
2014-03-03 |
|
US 90: J-Turns (Access Management) |
| H.009726.6-R1 - Miscellaneous |
| Proj. Engr: Landry, David N. |
Route: US 90 |
| Contractor: |
Miles: 1.25 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2012-12-10 |
$4,899,537 |
2013-10-03 |
|
I-10 @ La 328 (Breaux Bridge) Interchange Lighting |
| H.009786.6 - Roadway lighting |
| Proj. Engr: Woods, Seth |
Route: I-10 |
| Contractor: Webster Electric Co., Inc. |
Miles: 0.95 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2013-05-20 |
$695,244 |
2014-05-02 |
|
Little Platte Canal and Creek Bridges |
| 850-02-0015 - New location/replacement of bridge |
| Proj. Engr: Landry, David N. |
Route: |
| Contractor: Rcs Contractors, Inc. |
Miles: 4.35 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2011-10-10 |
$1,436,166 |
2012-09-18 |
St. Mary Parish
Note: The estimated completion date is based
on the work order date and the contract days
allowed.
|
Franklin Schools Sidewalk Project |
| H.007338.6 - Sidewalks/bike paths |
| Proj. Engr: Hidalgo, David |
Route: |
| Contractor: Byron E. Talbot Contractor, In |
Miles: 0.00 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2012-08-13 |
$440,365 |
2013-03-14 |
|
Catherine Street Sidewalk |
| H.007574.6 - Sidewalks/bike paths |
| Proj. Engr: Caillouet, Melanie |
Route: |
| Contractor: Hhp Construction Group LLC |
Miles: 0.50 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2012-03-29 |
$95,257 |
2012-07-29 |
|
LA 87: La 670 - La 324 |
| H.009643.6 - Asph concrete ovly over in place stabilized/cement treated base course |
| Proj. Engr: Deblanc, Frank |
Route: LA 87 |
| Contractor: Glenn Lege Construction Inc |
Miles: 4.37 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2013-01-10 |
$2,688,431 |
2013-08-25 |
|
Bayou Ramos US 90 Cracked Girder Structural Repairs |
| H.009990.6 - Bridges reconditioned |
| Proj. Engr: Deblanc, Frank |
Route: US 90 |
| Contractor: Gibson & Associates Inc. |
Miles: 0.00 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2013-01-11 |
$746,344 |
2014-04-09 |
Vermilion Parish
Note: The estimated completion date is based
on the work order date and the contract days
allowed.
|
LA 35: La 82 - La 335 |
| H.002116.6 - Asphalt overlay of asphalt pavement |
| Proj. Engr: Woods, Seth |
Route: LA 35 |
| Contractor: Glenn Lege Construction Inc |
Miles: 8.14 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2013-02-02 |
$3,428,616 |
2013-10-23 |
|
Perry Lift Bridge Mechanical Repairs |
| H.009095.6 - Moveable bridges reconditioned |
| Proj. Engr: Woods, Seth |
Route: LA 82 |
| Contractor: Coastal Bridge Co., L.L.C. |
Miles: 0.00 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2012-11-05 |
$1,116,000 |
2013-11-03 |
|
LA 14: Cameron P/L - Zwan Rd. |
| H.009641.6 - Asph concrete ovly over in place stabilized/cement treated base course |
| Proj. Engr: Chachere, Nicholas |
Route: LA 14 |
| Contractor: Glenn Lege Construction Inc |
Miles: 1.12 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2013-04-05 |
$772,989 |
2013-06-25 |
|
LA 14: E. C/L Gueydan - La 3093 |
| H.009642.6 - Asphalt overlay of asphalt pavement |
| Proj. Engr: Woods, Seth |
Route: LA 14 |
| Contractor: Coastal Bridge Co., L.L.C. |
Miles: 6.38 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2013-02-25 |
$3,203,360 |
2013-11-25 |
|
Bayou Tigre Bridge Repairs |
| 397-03-0022 - Moveable bridges reconditioned |
| Proj. Engr: Begnaud, Jerry |
Route: LA 330 |
| Contractor: Boland Marine & Manufact. Co L |
Miles: 0.00 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2010-04-16 |
$544,484 |
2010-10-14 |
District 03
|
District 03 Pavement Marking Replacement II |
| H.009057.6 - Striping and pavement markers |
| Proj. Engr: Deblanc, Frank |
Route: |
| Contractor: Pavement Markings, LLC |
Miles: 0.00 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2012-08-01 |
$1,252,753 |
2013-05-01 |
|
Dist 03 Signal & Beacon Upgrades |
| H.009154.6 - Signalization |
| Proj. Engr: Deblanc, Frank |
Route: |
| Contractor: Ernest P. Breaux Electrical, I |
Miles: 0.00 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2012-08-14 |
$994,818 |
2013-08-25 |
|
District 03 Signal Upgrades |
| H.009168.6 - Signalization |
| Proj. Engr: Faust, Jeff |
Route: |
| Contractor: Ernest P. Breaux Electrical, I |
Miles: 0.00 |
| Work Order Date |
Contract Amount |
Estimated Completion Date |
|
| 2013-01-15 |
$1,381,875 |
2013-11-24 |