Projects Under Construction

District 62

    Updated 11 Mar 2010

Districtwide Projects

Livingston Parish

Note: The estimated completion date is based on the work order date and the contract days allowed.

Amite River Bridge and Approaches
013-05-0044 - New location/replacement of bridge
Proj. Engr: Wascom, Kris     Route: US 190
Contractor: James Construction Group LLC     Miles: 2.30
Work Order Date Contract Amount Estimated Completion Date
2007-11-05 $30,155,609 2011-02-05


Walker Landscaping Project
268-01-0015 - Miscellaneous
Proj. Engr: Zzzz Hollowell, Clay     Route: LA 447 I-12
Contractor: Twin Shores Lands. & Const Serv I     Miles: 1.30
Work Order Date Contract Amount Estimated Completion Date
2009-03-23 $213,013 2009-07-23


Tickfaw River Bridge Near Starns
270-02-0018 - New location/replacement of bridge
Proj. Engr: Perilloux, Steve     Route: LA 441
Contractor: Coastal Bridge Co., L.L.C.     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2009-08-07 $3,415,802 2010-11-15


Turnlanes on La 64 & La 1026
273-03-0025 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Wascom, Kris     Route: LA 64 LA 1026
Contractor: Barber Bros. Contracting Co., L.L     Miles: 0.40
Work Order Date Contract Amount Estimated Completion Date
2009-01-08 $2,742,675 2009-09-12


I-12 Widening O'neal to Range
454-01-0047 - Concrete new pavement
Proj. Engr: Weick, Wayne     Route: I-12
Contractor: James Construction Group     Miles: 4.60
Work Order Date Contract Amount Estimated Completion Date
2008-12-30 $100,076,408 2012-01-14


I-12/La 43 Interchange Landscaping
454-02-0060 - Landscaping
Proj. Engr: Wascom, Kris     Route: I-12 LA 43
Contractor: Green Scapes of Louisiana Inc     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2008-05-28 $229,206 2008-09-27


I-12/La 63 Interchange Landscaping
454-02-0065 - Landscaping
Proj. Engr: Wascom, Kris     Route: I-12
Contractor: Green Scapes of Louisiana Inc     Miles: 0.45
Work Order Date Contract Amount Estimated Completion Date
2008-05-28 $229,206 2008-09-27


St. Helena Parish

Note: The estimated completion date is based on the work order date and the contract days allowed.

Killian Branch Creek Bridge
713-46-0101 - New location/replacement of bridge
Proj. Engr: Wascom, Kris     Route:
Contractor: Guinn Brothers, LLC.     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2009-12-25 $598,826 2010-07-26


St. John Baptist Parish

Note: The estimated completion date is based on the work order date and the contract days allowed.

US 61 Signal Upgrades
007-02-0097 - Signalization
Proj. Engr: Perilloux, Steve     Route: US 61
Contractor: Jack B. Harper Contractor, Inc.     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
1990-09-03 $4,597,075 1992-01-05


Laplace Pit Scale Mainline Sortng System
450-13-0042 - Weigh-in-motion
Proj. Engr: Perilloux, Steve     Route: I-10
Contractor: Toomer Electrical Co., Inc.     Miles: 4.27
Work Order Date Contract Amount Estimated Completion Date
2007-01-04 $3,088,736 2007-09-03


St. Tammany Parish

Note: The estimated completion date is based on the work order date and the contract days allowed.

LA 22 to Bayou Castine
013-12-0032 - Concrete new pavement
Proj. Engr: Sharp, Larry Jr     Route: US 190 LA 1087 LA 59
Contractor: Boh Bros. Construction Co., LLC.     Miles: 7.50
Work Order Date Contract Amount Estimated Completion Date
2006-10-16 $28,616,896 2009-05-21


Interchange Improvements US Highway 11 and Ramp Improvements
018-04-0046 - Clearing and grubbing
Proj. Engr: Hickman, Tommy Jr.     Route: US 11 I-12
Contractor: Barriere Construction Co., LLC.     Miles: 1.43
Work Order Date Contract Amount Estimated Completion Date
2009-09-25 $5,281,285 2010-06-25


Three Laning of La 41 In Pearl River
058-01-0026 - Asphalt new pavement-new roadway/new alignments
Proj. Engr: Hickman, Tommy Jr.     Route: LA 41
Contractor: Huey Stockstill, Inc.     Miles: 1.25
Work Order Date Contract Amount Estimated Completion Date
2009-03-02 $1,470,148 2009-10-07


Jct. US 190 Bypass - Jct. La 1129
279-01-0012 - Asphalt overlay of asphalt pavement
Proj. Engr: Sharp, Larry Jr     Route: LA 437 LA 40
Contractor: Barriere Construction Co., LLC     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2009-08-12 $3,085,361 2009-12-21


LA 59 at I-12 Interchange Improvements
281-03-0022 - Asphalt widening and overlay
Proj. Engr: Sharp, Larry Jr     Route: LA 59 I-12
Contractor: Barriere Construction Co., LLC.     Miles: 1.05
Work Order Date Contract Amount Estimated Completion Date
2009-08-22 $2,945,457 2010-04-12


LA 435 Bridges
281-04-0021 - Bridges reconditioned
Proj. Engr: Sharp, Larry Jr     Route: LA 435
Contractor: Diamond B Construction Co., L.L.C     Miles: 0.89
Work Order Date Contract Amount Estimated Completion Date
2009-03-30 $4,909,077 2010-05-18


I-10 Bridge Over Lake Pontchartrain
450-17-0025 - Miscellaneous
Proj. Engr: Zzzz Horn, John     Route: I-10
Contractor: Boh Bros. Construction Co., LLC.     Miles: 5.26
Work Order Date Contract Amount Estimated Completion Date
2006-06-01 $432,892,046 2012-06-18


Acrow Disassembly, Transportation, Relocation, and Storage
450-17-0032 - Buildings and grounds excluding rest areas
Proj. Engr: Horn, John     Route: I-10
Contractor: Boh Bros. Construction Co., LLC.     Miles: 5.41
Work Order Date Contract Amount Estimated Completion Date
2009-08-03 $4,296,445 2010-02-21


I-59 @ La 1090 Interchange Improvements
453-01-0058 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Hickman, Tommy Jr.     Route: I-59 LA 1090
Contractor: Boh Bros. Construction Co., LLC.     Miles: 0.96
Work Order Date Contract Amount Estimated Completion Date
2009-09-08 $1,279,032 2009-12-09


LA 1088 Interchange/ Route I-12
454-04-0038 - Concrete new pavement
Proj. Engr: Sharp, Larry Jr     Route:
Contractor: Barriere Construction Co., LLC     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2009-10-25 $12,255,217 2011-02-11


Tangipahoa Parish Line - Jct. US 190 (Covington)
454-04-0076 - Asphalt overlay of asphalt pavement
Proj. Engr: Sharp, Larry Jr     Route: I-12
Contractor: Barriere Construction Co., LLC.     Miles: 10.13
Work Order Date Contract Amount Estimated Completion Date
2009-05-11 $12,688,564 2009-12-13


Rest Area Improvements, I-10 at Slidell
690-03-0003 - Rest areas
Proj. Engr: Rodi, Ronald     Route:
Contractor: Barriere Construction Co., LLC.     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2008-03-24 $12,177,947 2009-08-03


Carr Drive Bridge
713-52-0100 - New location/replacement of bridge
Proj. Engr: Ray, James     Route:
Contractor: Key Constructors, Inc.     Miles: 0.07
Work Order Date Contract Amount Estimated Completion Date
2009-08-15 $2,373,415 2010-04-08


Jct. La 1077 - Jct. La 25
852-06-0008 - Asphalt overlay of asphalt pavement
Proj. Engr: Hickman, Tommy Jr.     Route: LA 1077 LA 1078
Contractor: Diamond B Construction Co., L.     Miles: 6.20
Work Order Date Contract Amount Estimated Completion Date
2009-06-08 $2,346,085 2009-10-22


Bayou Liberty Bridge and Approaches (Bonfouca)
852-21-0024 - New location/replacement of bridge
Proj. Engr: Sharp, Larry Jr     Route: LA 433
Contractor: Coastal Bridge Co., L.L.C.     Miles: 0.13
Work Order Date Contract Amount Estimated Completion Date
2007-01-01 $6,382,927 2009-11-24


Tangipahoa Parish

Note: The estimated completion date is based on the work order date and the contract days allowed.

LA 10 - Junction La 1049
452-90-0125 - Asphalt overlay of asphalt pavement
Proj. Engr: Perilloux, Steve     Route: I-55
Contractor: Diamond B Construction Co., L.L.C     Miles: 7.33
Work Order Date Contract Amount Estimated Completion Date
2008-03-03 $19,844,638 2009-11-26


Jct. La 16 - Jct. La 10
452-90-0153 - Asphaltic concrete overlay of rubblized pavement
Proj. Engr: Perilloux, Steve     Route: I-55
Contractor: Diamond B Construction Co., L.     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2009-09-27 $17,676,687 2010-09-29


I-12 at La 3158 (S. Airport)
454-03-0069 - Roadway lighting
Proj. Engr: Perilloux, Steve     Route: I-12
Contractor: Diamond Electrical Co., Inc.     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2009-08-08 $457,862 2010-05-12


Baptist Weigh Station
690-27-0009 - Pit scales
Proj. Engr: Perilloux, Steve     Route: I-12
Contractor: Diamond Electrical Co., Inc.     Miles: 1.00
Work Order Date Contract Amount Estimated Completion Date
2008-12-08 $784,191 2009-06-07


J.W. Davis & Little Italy Road Bridges
713-53-0112 - New location/replacement of bridge
Proj. Engr: Langenstein, Larry     Route:
Contractor: Key Constructors, Inc.     Miles: 0.14
Work Order Date Contract Amount Estimated Completion Date
2009-06-29 $1,433,694 2010-01-14


Realignment of La 1040
853-10-0016 - Asphalt new pavement-new roadway/new alignments
Proj. Engr: Perilloux, Steve     Route: LA 1040
Contractor: Byron E. Talbot Contractor, Inc.     Miles: 0.38
Work Order Date Contract Amount Estimated Completion Date
2009-07-01 $1,665,908 2009-12-20


Jct. La 442/443 - Jct. La 1062
853-27-0023 - Asph concrete ovly over in place stabilized/cement treated base course
Proj. Engr: Perilloux, Steve     Route: LA 40
Contractor: Diamond B Construction Co., L.     Miles: 2.00
Work Order Date Contract Amount Estimated Completion Date
2009-11-16 $720,129 2010-03-08


.596 Mile South of La 442 Jct. - 2 Miles South of US 51 Jct.
853-33-0016 - Asphalt overlay of asphalt pavement
Proj. Engr: Perilloux, Steve     Route: LA 1065
Contractor: Barriere Construction Co., LLC     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2009-11-30 $1,406,637 2010-03-12


Intersection Improvements at Old Covington Hwy
853-39-0008-R1 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Perilloux, Steve     Route: LA 3158
Contractor: Barriere Construction Co., LLC     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2009-10-11 $549,386 2010-02-17


Washington Parish

Note: The estimated completion date is based on the work order date and the contract days allowed.

Bridges In Washington Parish
713-59-0211 - New location/replacement of bridge
Proj. Engr: Aucoin, Andre'     Route:
Contractor: Command Construction Industries L     Miles: 0.32
Work Order Date Contract Amount Estimated Completion Date
2009-08-10 $1,596,074 2010-03-29


District 62

No districtwide projects.