Projects Under Construction

District 58

    Updated 20 Aug 2008

Districtwide Projects

Caldwell Parish

Note: The estimated completion date is based on the work order date and the contract days allowed.

Grayson - Columbia
015-06-0030 - Concrete new pavement
Proj. Engr: Reeves, Justin     Route: US 165 LA 126
Contractor: Denton-James LLC     Miles: 8.94
Work Order Date Contract Amount Estimated Completion Date
2004-09-15 $26,346,923 2007-10-16


State Route In Columbia
015-06-0038 - Concrete new pavement
Proj. Engr: West, Neal     Route: US 165
Contractor: Jensen Construction Co.     Miles: 2.68
Work Order Date Contract Amount Estimated Completion Date
2003-10-06 $27,686,404 2006-11-23


State Route In Columbia (Main Spans) Route US 165
015-07-0047 - New location/replacement of bridge
Proj. Engr: West, Neal     Route: US 165
Contractor: Jensen Construction Co.     Miles: 0.19
Work Order Date Contract Amount Estimated Completion Date
2001-09-17 $22,040,559 2004-11-23


Catahoula Parish

Note: The estimated completion date is based on the work order date and the contract days allowed.

Black River Bridge and Approaches,Jonesville, La
022-06-0040 - New location/replacement of bridge
Proj. Engr: Reeves, Justin     Route: US 84
Contractor: James Construction Group LLC     Miles: 2.16
Work Order Date Contract Amount Estimated Completion Date
2006-02-01 $31,514,674 2010-02-23


Jonesville Cl - West Jct La 927
022-06-0048 - Asphalt overlay of asphalt pavement
Proj. Engr: Reeves, Justin     Route: US 84
Contractor: Gilchrist Construction Co. LLC     Miles: 1.66
Work Order Date Contract Amount Estimated Completion Date
2008-02-09 $2,944,342 2008-08-21


Districtwide Asphaltic Surface Treatment Projects
130-02-0016 - Asphalt surface treatment
Proj. Engr: Panteria, Gary     Route: LA 503 LA 916 LA 1017 LA 1018-1 LA 600
Contractor: Dreher Contracting, Inc.     Miles: 29.43
Work Order Date Contract Amount Estimated Completion Date
2008-08-01 $937,948 2008-12-21


Concordia Parish

Note: The estimated completion date is based on the work order date and the contract days allowed.

Black River Bridge and Approaches,Jonesville, La
022-06-0040 - New location/replacement of bridge
Proj. Engr: Reeves, Justin     Route: US 84
Contractor: James Construction Group LLC     Miles: 2.16
Work Order Date Contract Amount Estimated Completion Date
2006-02-01 $31,514,674 2010-02-23


Vidalia - Ferriday (Turn Lanes)
026-02-0060 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Roussell, Chris     Route: US 65
Contractor: W. E. Blain & Sons, Inc.     Miles: 5.17
Work Order Date Contract Amount Estimated Completion Date
2008-02-26 $1,139,335 2008-07-08


Districtwide Asphaltic Surface Treatment Projects
130-02-0016 - Asphalt surface treatment
Proj. Engr: Panteria, Gary     Route: LA 503 LA 916 LA 1017 LA 1018-1 LA 600
Contractor: Dreher Contracting, Inc.     Miles: 29.43
Work Order Date Contract Amount Estimated Completion Date
2008-08-01 $937,948 2008-12-21


Franklin Parish

Note: The estimated completion date is based on the work order date and the contract days allowed.

Gilbert Concrete Section (P.M.)
026-06-0058 - Portland Cement Pavement patch
Proj. Engr: Parks, Chad H.     Route: LA 15
Contractor: Forby Contracting, Inc.     Miles: 1.53
Work Order Date Contract Amount Estimated Completion Date
2008-06-08 $241,248 2008-09-08


Tensas River Bridge and Approaches
036-04-0050 - New location/replacement of bridge
Proj. Engr: Free, James K.     Route: LA 4
Contractor: James Construction Group LLC     Miles: 1.07
Work Order Date Contract Amount Estimated Completion Date
2007-03-05 $6,826,965 2008-05-11


LaSalle Parish

Note: The estimated completion date is based on the work order date and the contract days allowed.

Georgetown- Tullos
015-04-0039 - Concrete new pavement
Proj. Engr: Johnson, Theodore     Route: US 165
Contractor: Gilchrist Construction Co. LLC     Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2007-07-09 $46,388,479 2009-11-26


Districtwide Asphaltic Surface Treatment Projects
130-02-0016 - Asphalt surface treatment
Proj. Engr: Panteria, Gary     Route: LA 503 LA 916 LA 1017 LA 1018-1 LA 600
Contractor: Dreher Contracting, Inc.     Miles: 29.43
Work Order Date Contract Amount Estimated Completion Date
2008-08-01 $937,948 2008-12-21


Tensas Parish

Note: The estimated completion date is based on the work order date and the contract days allowed.

LA 568 North - La 128 North
020-02-0033 - Asphalt overlay of asphalt pavement
Proj. Engr: Parks, Chad H.     Route: US 65
Contractor: D & J Construction Co., Inc.     Miles: 9.88
Work Order Date Contract Amount Estimated Completion Date
2008-01-14 $3,848,118 2008-08-15


Tensas River Bridge and Approaches
036-04-0050 - New location/replacement of bridge
Proj. Engr: Free, James K.     Route: LA 4
Contractor: James Construction Group LLC     Miles: 1.07
Work Order Date Contract Amount Estimated Completion Date
2007-03-05 $6,826,965 2008-05-11


District 58

No districtwide projects.