Project Details:
State Proj. No.: 450-15-0089
Start date: February 2006
Finish date: October 2008
Cost: $68,841,489
Contractor: Boh Brothers Const.
I-10 Expansion in Jefferson Parish:

The expansion of I-10 from Causeway Boulevard to the 17th Street Canal will relieve traffic congestion at the Causeway Boulevard interchange. Traffic congestion has been steadily increasing in this area for years as a result of the rapid population growth and urban development occurring on Lake Pontchartrain’s north shore. This section of I-10 is one of the most traveled roads in Louisiana.

Work on the 1.9-mile stretch of interstate includes adding a fourth lane on each side of the roadway, constructing a second lane on the entrance and exit ramps at the Causeway and Bonnabel Boulevard interchanges, and the relocation and upgrade of water and sewer mains along the I-10 service roads.

The new roadway is being constructed with asphalt that is formulated to lengthen the life of the pavement and lower long-term maintenance and repair costs.




Project Gallery

 
   Thursday, August 21, 2008
CONTACTS LINKS SITE MAP
The La DOTD Headquarters Building is located at 1201 Capitol Access Road, Baton Rouge, LA, 70804-9245. Telephone: (225) 379-1232.
Please send us your Comments or Suggestions.