State Proj. No.: 450-15-0089
Start date: February 2006
Finish date: May 2009
Cost: $68,841,489
Contractor: Boh Brothers Const.
The expansion of I-10 from Causeway Boulevard to the 17th Street Canal will relieve traffic congestion at
the Causeway Boulevard interchange. Traffic congestion has been steadily increasing in this area for years
as a result of the rapid population growth and urban development occurring on Lake Pontchartrain's north
shore. This section of I-10 is one of the most traveled roads in Louisiana.
Work on the 1.9-mile stretch of interstate includes adding a fourth lane on each side of the roadway, constructing
a second lane on the entrance and exit ramps at the Causeway and Bonnabel Boulevard interchanges, and the relocation
and upgrade of water and sewer mains along the I-10 service roads.
The new roadway is being constructed with asphalt that is formulated to lengthen the life of the pavement and lower
long-term maintenance and repair costs.